Highway Project WBS │ ├── 1. Project Management │ ├── 1.1 Project Initiation │ ├── 1.2 Project Planning │ ├── 1.3 Project Execution │ ├── 1.4 Monitoring and Control │ └── 1.5 Project Closeout │ ├── 2. Engineering (Design) │ ├── 2.1 Geotechnical Surveys and Soil Testing │ ├── 2.2 Topographic Surveys │ ├── 2.3 Detailed Road Design │ │ ├── 2.3.1 Alignment Design │ │ ├── 2.3.2 Pavement Design │ │ ├── 2.3.3 Drainage Design │ │ └── 2.3.4 Safety and Traffic Control Design │ ├── 2.4 Utility Relocation Plans │ ├── 2.5 Environmental Impact Assessment (EIA) │ ├── 2.6 Design Approvals and Permits │ └── 2.7 Detailed Construction Drawings │ ├── 3. Procurement │ ├── 3.1 Material Procurement │ │ ├── 3.1.1 Asphalt Materials │ │ ├── 3.1.2 Aggregates and Base Materials │ │ ├── 3.1.3 Reinforcement Steel │ │ ├── 3.1.4 Concrete for Bridge Structures (if applicable) │ │ └── 3.1.5 Road Signs and Safety Equipment │ ├── 3.2 Equipment Procurement │ │ ├── 3.2.1 Excavators and Earthmoving Equipment │ │ ├── 3.2.2 Compaction Equipment │ │ ├── 3.2.3 Pavers and Mixers │ │ └── 3.2.4 Traffic Control Equipment │ ├── 3.3 Subcontractor Selection │ └── 3.4 Procurement of Temporary Facilities (e.g., offices, utilities) │ ├── 4. Construction │ ├── 4.1 Mobilization │ │ ├── 4.1.1 Site Setup │ │ ├── 4.1.2 Temporary Facilities Setup │ │ └── 4.1.3 Workforce Mobilization │ ├── 4.2 Earthworks and Excavation │ │ ├── 4.2.1 Site Clearing │ │ ├── 4.2.2 Excavation and Grading │ │ └── 4.2.3 Embankment Construction │ ├── 4.3 Pavement Construction │ │ ├── 4.3.1 Subbase and Base Course Installation │ │ ├── 4.3.2 Asphalt Layering │ │ └── 4.3.3 Quality Control for Pavement │ ├── 4.4 Drainage and Utilities │ │ ├── 4.4.1 Stormwater Drainage Installation │ │ ├── 4.4.2 Utility Relocation and Installation │ │ └── 4.4.3 Erosion and Sediment Control │ ├── 4.5 Road Signage and Marking │ │ ├── 4.5.1 Signage Installation │ │ └── 4.5.2 Road Markings │ ├── 4.6 Traffic Control and Safety Measures │ │ ├── 4.6.1 Temporary Traffic Diversion Setup │ │ └── 4.6.2 Safety Barriers and Guardrails │ ├── 4.7 Bridge or Overpass Construction (if applicable) │ │ ├── 4.7.1 Foundation and Substructure Works │ │ ├── 4.7.2 Superstructure and Deck Works │ │ └── 4.7.3 Deck Finishing and Waterproofing │ ├── 4.8 Final Roadworks and Surface Finishing │ │ ├── 4.8.1 Final Grading and Surface Leveling │ │ └── 4.8.2 Final Asphalt Layer and Compacting │ ├── 4.9 Testing and Commissioning │ │ ├── 4.9.1 Pavement and Surface Testing │ │ └── 4.9.2 Road Safety Testing │ └── 4.10 Demobilization │ ├── 4.10.1 Site Cleanup │ └── 4.10.2 Equipment and Personnel Demobilization │ └── 5. Quality Assurance and Control ├── 5.1 Material Inspection and Testing ├── 5.2 Construction Inspection ├── 5.3 Compliance Audits └── 5.4 Final Quality Reports
Work Breakdown Structure (WBS) Development
Explore top LinkedIn content from expert professionals.
-
-
🔹 From BOQ to Schedule: How to Map Scope into WBS & Activities Every project begins with a BOQ (Bill of Quantities) – a structured list of items, quantities, and costs. But for planners, this is not enough. To execute and control the work, we need to translate the BOQ into a detailed Work Breakdown Structure (WBS) and activities inside Primavera P6. ✅ Step 1: Scope Mapping The BOQ describes what needs to be done. For example, under Construction of Watch Towers, the BOQ includes: Excavation & foundation work Concrete pouring & formwork Reinforcement steel fixing Masonry & plaster works Doors, windows, and finishing Each of these naturally maps into Level-3 or Level-4 WBS nodes in Primavera P6. ✅ Step 2: Tools & Techniques WBS Dictionary → Define each scope item with clear deliverables. Decomposition Technique → Break BOQ items into smaller manageable activities. Quantity-to-Duration Conversion → Use productivity norms to estimate durations (e.g., 386 sqm plaster @ 20 sqm/day = ~20 days). Logical Sequencing → Link excavation → foundation → reinforcement → concreting → superstructure → finishes. Resource Loading → Map manpower, equipment, and materials against each BOQ item. ✅ Step 3: Example Transformation From the BOQ “Watch Tower” (Excel shown above): Excavation (8 Cum) → Activity: Excavation in Foundation Concrete (8,000 Cum) → Activity: Concrete Works (PCC + RCC) Reinforcement (7,560 Kg) → Activity: Rebar Cutting, Bending, Fixing Plaster (386 sqm) → Activity: Internal & External Plaster Doors & Windows (Jobs & Sqm) → Activity: Doors & Windows Installation Finishing Works (Tiles, Paint, Weather Shield) → Activity: Finishing & Protection Works Mapped in Primavera P6 WBS Structure as: L1: Airport Project L2: Buildings L3: Watch Tower L4: Foundation Works L4: Structural Concrete L4: Reinforcement Works L4: Masonry & Plaster L4: Doors & Windows L4: Finishing & Protection ✅ Value for Planners This transformation allows: Better scope control Integration of cost (BOQ) with time (schedule) Effective progress measurement by discipline/activity Smooth reporting with Earned Value 📌 Want to see how this BOQ was transformed into a P6 Schedule with WBS + Activities? 💬 Write “Construction Project P6 file” & I’ll share the sample Primavera P6 XER file with you!
-
Here is an example of a Work Breakdown Structure (WBS) for a Infrastructure Construction Project : 1. Project Management • 1.1 Project Initiation • 1.1.1 Stakeholder Identification and Engagement • 1.1.2 Feasibility Study and Preliminary Planning • 1.1.3 Contract Negotiation and Signing • 1.2 Project Planning • 1.2.1 Work Plan and Resource Allocation • 1.2.2 Scheduling and Budgeting • 1.2.3 Risk Analysis and Contingency Planning • 1.3 Project Execution • 1.3.1 Team Coordination and Communication • 1.3.2 Documentation and Progress Tracking • 1.4 Monitoring and Control • 1.4.1 Cost Monitoring and Variance Analysis • 1.4.2 Schedule Control and Adjustments • 1.4.3 Quality and Safety Assurance • 1.5 Project Closeout • 1.5.1 Final Reporting and Documentation • 1.5.2 Stakeholder Handover and Acceptance • 1.5.3 Lessons Learned and Post-Evaluation 2. Design and Approvals • 2.1 Feasibility Studies and Preliminary Design • 2.1.1 Site Investigation and Survey • 2.1.2 Geotechnical Studies • 2.1.3 Concept Design Development • 2.2 Detailed Design • 2.2.1 Structural Design (e.g., bridges, foundations, tunnels) • 2.2.2 Civil Design (e.g., roads, drainage, earthworks) • 2.2.3 MEP Design (e.g., utilities, lighting, mechanical systems) • 2.3 Regulatory Approvals • 2.3.1 Environmental Impact Assessments (EIA) • 2.3.2 Permits and Licenses • 2.3.3 Safety and Compliance Approvals 3. Procurement • 3.1 Materials Procurement • 3.1.1 Structural Steel • 3.1.2 Cement and Concrete • 3.1.3 Aggregates and Asphalt • 3.1.4 Pipes, Fittings, and Drainage Systems • 3.1.5 Electrical Components (e.g., cables, lighting poles) • 3.2 Equipment Procurement • 3.2.1 Heavy Machinery (e.g., cranes, excavators, pavers) • 3.2.2 Specialized Tools and Equipment • 3.3 Subcontractor Selection • 3.3.1 Bid Evaluation • 3.3.2 Contract Negotiation and Award • 3.4 Procurement of Temporary Facilities • 3.4.1 Site Offices • 3.4.2 Storage Yards and Worker Camps 4. Construction • 4.1 Site Preparation • 4.1.1 Site Clearing and Leveling • 4.1.2 Temporary Utilities Setup (Power, Water, Drainage) • 4.1.3 Excavation and Earthworks • 4.2 Foundation Works • 4.2.1 Geotechnical Preparations (e.g., piling, soil stabilization) • 4.2.2 Foundation Installation (e.g., reinforced concrete or deep foundations) • 4.3 Superstructure Construction • 4.3.1 Structural Framework (e.g., bridges, tunnels, dams) • 4.3.2 Slab Construction (e.g., roads, platforms, decks) • 4.3.3 Assembly and Erection (e.g., steel girders, beams) • 4.4 Roadworks and Paving • 4.4.1 Subgrade Preparation and Compaction • 4.4.2 Base and Subbase Layer Installation • 4.4.3 Asphalt or Concrete Paving • 4.5 Drainage and Utilities • 4.5.1 Installation of Drainage Systems (e.g., culverts, pipes) • 4.5.2 Sewerage and Water Supply Systems • 4.5.3 Electrical and Communication Infrastructure • 4.6 Landscaping and Finishing • 4.6.1 Roadside Landscaping (e.g., planting, grading)
-
WBS in piping project 1.0 Project Initiation & Planning 1.1 Project Planning 1.1.1 Project Charter 1.1.2 Project Scope Definition 1.1.3 Work Breakdown Structure (This document) 1.1.4 Schedule Development 1.1.5 Budget Estimation 1.1.6 Risk Assessment 1.1.7 Procurement Plan 1.1.8 Quality Plan 1.1.9 Communication Plan 1.1.10 Stakeholder Management Plan 2.0 Engineering & Design 2.1 Piping & Instrumentation Diagram (P&ID) Development 2.2 Pipe Routing & Support Design 2.3 Material Take-Off (MTO) 2.3.1 Pipe 2.3.2 Valves 2.3.3 Fittings 2.3.4 Supports 2.3.5 Insulation 2.3.6 Instrumentation 3.0 Procurement 3.1 Material Procurement 3.1.1 Pipe Procurement 3.1.2 Valve Procurement 3.1.3 Fitting Procurement 3.1.4 Insulation Procurement 3.1.5 Instrumentation Procurement 3.2 Equipment Procurement 3.2.1 Pumps 3.2.2 Compressors 3.2.3 Heat Exchangers 4.0 Fabrication & Assembly 4.1 Pipe Fabrication 4.1.1 Cutting 4.1.2 Bending 4.1.3 Welding 4.1.4 Flange Facing 4.2 Pipe Support Fabrication 4.3 Equipment Assembly 5.0 Site Construction 5.1 Site Preparation 5.2 Pipe Installation 5.2.1 Pipe Support Installation 5.2.2 Pipe Joint Welding 5.2.3 Pipe Insulation 5.3 Equipment Installation 5.4 Piping Stress Analysis & Alignment 6.0 Testing & Commissioning 6.1 Pressure Testing 6.2 Hydrostatic Testing 6.3 Leak Testing 6.4 Functional Testing 6.5 System Commissioning 7.0 Pre-Commissioning & Commissioning 7.1 Pre-commissioning Activities 7.1.1 Flushing 7.1.2 Drying 7.1.3 Cleaning 7.2 Commissioning Activities 7.2.1 System Start-up 7.2.2 Performance Testing 7.2.3 System Hand-over 8.0 Documentation & Closeout 8.1 As-Built Drawings 8.2 Test Reports 8.3 Inspection Reports 8.4 Project Closeout Documents Note: This is a general framework. The specific WBS will vary depending on the scope, complexity, and requirements of the individual piping project. Factors such as the type of piping system (e.g., process piping, HVAC, fire protection), the industry (oil & gas, chemical, pharmaceutical), and the project location will all influence the specific activities and their breakdown. This WBS can be further detailed by adding more levels and specific tasks within each work package. For example, under "Pipe Fabrication," you could include tasks like "Cutting & beveling," "Tack welding," "Full penetration welding," "Non-destructive testing (NDT)," etc. By using a well-defined WBS, project teams can effectively plan, execute, and track progress on piping projects.
-
Work Breakdown Structure (WBS): It is a hierarchical decomposition of the project scope into manageable and smaller components, ensuring every aspect of the project is accounted for. How WBS is Helpful? Activity List: WBS simplifies identifying all project activities, ensuring nothing is overlooked. Control: By breaking down tasks, it provides better control over the project. Risk Management: Smaller components make it easier to identify, analyze, and mitigate risks. Quality Assurance: Clear deliverables at every level enhance quality control. Budgeting: Each task's budget is assigned more accurately. Estimating: It enables realistic cost and time estimates. Procurement: Facilitates procurement planning by detailing required resources and contracts. Resources Allocation: Ensures efficient distribution of human and material resources. Network Diagram: Serves as a foundation for creating network diagrams to visualize project workflows. How WBS is Created? WBS is developed with the help of: Contracts: Ensure alignment with agreed terms. Scope of Work (SOW): Define what needs to be delivered. BOQ (Bill of Quantities): Identify all necessary materials and quantities. Drawings: Provide visual guidance on the deliverables. Tender Documents: Offer comprehensive project requirements. Stakeholder Meetings: Ensure alignment with all parties involved. Key Rules of WBS: Hierarchical Structure: Each level is a smaller segment of the level above it. Granularity: Some levels may need further breakdown depending on complexity. Lowest Level: Includes Work Packages, which are actionable components. What Defines a Work Package? Realistic Estimation: Work Packages can be accurately estimated for cost and time. Budget: Each package is assigned a specific budget. Duration: It has a limited time frame and cost. Outsourcing: Can be contracted or outsourced if necessary. 4% Rule: Should constitute at least 4% of the total project scope. Unique Deliverables: Each package must result in a unique, identifiable output. Approaches to Developing a WBS: Physical Space Approach: Organize by physical areas (e.g., building floors or sections). Phase Approach: Break down by project phases, such as design, construction, and testing. EPC Approach: Decompose by Engineering, Procurement, and Construction. CSI Master Format: Utilize the Construction Specifications Institute's standard for organization. #ProjectManagement #Planning #Scheduling #ScheduleBaseline #RevisedAndRecoverySchedule #ProjectControl #CostControl #TimeControl #DelayAnalysis #DelayClaims #ResourceManagement #RiskManagement #ChangeManagement #NEOM #KSA
-
Schedule % Complete vs. Performance % Complete for WBS and Activity level in Primavera P6: ---------------------------------------------------------------------- Q: Why the Plan % and Actaul % are different, even though the WBS has only one activity? A: Well, to answer this question, we want to know how each one is calculated. 1- Schedule % Complete: a) For Activity level: ([DD] – [BL SD]) / ([BL FD] – [BL SD]) b) For WBS level: will be the ratio of the "Baseline Costs" before the Data Date to the "Total Baseline Cost", which means = PV / BAC. Conclusion: To recap, Schedule % Complete for "Activities" is based on "time", while for "WBS" is based on "costs". 2- Performance % Complete: There are five options for selecting Performance % Complete as shown in the screenshot below. The selection is made at the WBS level and prevails in all activities within this WBS. The most common technique used is "Activity % Complete" and calculated as "Earned Value Cost" based on the Activity’s % complete. Primavera P6 provides us with three options for identifying Activity % Complete. These calculations are listed below: Duration % Complete = [(OD – RD)/OD]*100. Units % Complete = (Actual Units/At Completion Units) * 100 Physical % Complete = based on personal judgment. I've attached the screenshot demonstrating how each one works. Conclusion: To recap, Performance % complete is calculated as (BCWP "EV" * 100) / BAC, regardless of what earned value technique is selected for the activity's WBS. PV: Planned Value BAC: Budgeted At Completion DD: Data Date BL SD: Baseline Start BL FD: Baseline Finish OD: Original Duration RD: Remaining Duration The example below is to test your understanding. #A_Y_Tips
-
🚀 Tracking Physical Progress and Costs in Primavera P6 for a High-Stakes Fast-Track Project Managing a fast-track project presents a major challenge: keeping progress and costs under control without having the full engineering package finalized. In these cases, precise tracking in Primavera P6 is essential to mitigate cost overruns and schedule slippages. Here’s how to execute it effectively, along with the key personnel responsible for each phase. ✅ 1. Structuring the WBS and Planning in a High-Uncertainty Environment 📌 Responsible: Project Planner / Project Controls 📌 Develop a Work Breakdown Structure (WBS) with a modular and adaptable approach. 📌 Utilize placeholder activities to account for pending design releases. 📌 Implement smart activity coding to differentiate engineering, procurement, and construction (EPC) phases. ✅ 2. Measuring Physical Progress with an Evolving Engineering Scope 📌 Responsible: Project Planner / Site Supervisor 📌 Select the most appropriate progress measurement methodology: 🔹 Physical % Complete for tangible construction activities. 🔹 Units % Complete for resource-intensive operations. 🔹 Weighted Steps for multi-deliverable work packages. 📌 The engineering team must update deliverables based on actual site progress. 📌 With an incomplete design, progress tracking must be dynamically recalculated as new engineering packages are released. ✅ 3. Cost Tracking in a Constantly Evolving Scope 📌 Responsible: Cost Controller / Finance Team 📌 Implement Earned Value Management (EVM) with adjustable cost assumptions. 📌 Maintain a parallel control system comparing budgeted vs. actual costs per work package. 📌 Key Performance Indicators (KPIs): 🔹 CPI (Cost Performance Index): Measures cost efficiency. 🔹 SPI (Schedule Performance Index): Assesses schedule adherence. 🔹 TCPI (To-Complete Performance Index): Predicts future cost deviations. ✅ 4. Real-Time Data Tracking with Dynamic Reporting Tools 📌 Responsible: Project Planner / Data Analyst / IT Support 📌 Integrate Primavera P6 with Power BI to generate real-time dashboards. 📌 Leverage “What-If” scenario analysis in P6 to anticipate design-related delays. 📌 Develop dynamic Excel-based reports with macros for cost forecasting adjustments. 💡 Conclusion: In a high-stakes fast-track project, the key to success lies in flexible planning and real-time data-driven decision-making. Applying these strategies in Primavera P6 enables project teams to stay ahead of risks and maintain cost control. 🔹 How do you manage control in high-uncertainty projects? Share your insights in the comments! #ProjectManagement #ProgramManagement #ConstructionPlanning #EngineeringManagement #PMO #PMP #PMI #ProjectControls #EPCM #PlanningEngineer #FastTrackProjects #CostControl #RiskManagement #KPI #ScheduleTracking #BudgetManagement #PerformanceMonitoring #EPCProjects #ConstructionManagement #HeavyCivilEngineering #InfrastructureProjects #MegaProjects #OilAndGas
-
𝑩𝒆𝒔𝒕 𝑷𝒓𝒂𝒄𝒕𝒊𝒄𝒆𝒔 𝑩𝒂𝒔𝒆𝒅 𝑰𝒏𝒕𝒆𝒈𝒓𝒂𝒕𝒆𝒅 𝑷𝒓𝒐𝒋𝒆𝒄𝒕 𝑴𝒐𝒏𝒊𝒕𝒐𝒓𝒊𝒏𝒈 & 𝑪𝒐𝒏𝒕𝒓𝒐𝒍 Successful projects deliver their scope with quality within agreed upon time & cost Integrated Monitoring & Controlling of schedule, scope, cost, risks, resources & quality throughout project’s life cycle starting from project planning till asset transition is mandatory for project success While most of leading project management frameworks like PMBOK by (PMI), PRINCE2 by Axelos, TCM framework by AACE, LEAN & Agile support this, each one of them have their strengths. While some are well suited for traditional projects with longer milestones (EPC), others fit well for projects which calls for inter-disciplinary team work within shorter milestones (R&D, Early phases of EPC, Snagging etc). 𝐁𝐞𝐬𝐭 𝐏𝐫𝐚𝐜𝐭𝐢𝐜𝐞𝐬 𝐁𝐚𝐬𝐞𝐝 𝐈𝐧𝐭𝐞𝐠𝐫𝐚𝐭𝐞𝐝 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐌𝐨𝐧𝐢𝐭𝐨𝐫𝐢𝐧𝐠 & 𝐂𝐨𝐧𝐭𝐫𝐨𝐥 𝐏𝐡𝐚𝐬𝐞 𝟏: 𝐏𝐫𝐞𝐩𝐚𝐫𝐚𝐭𝐢𝐨𝐧 Focus–Get ready for planning phase Scope definition(PMBOK, TCM, PRINCE2,Agile) Stakeholder identification(PMBOK) Role definition(PMBOK, TCM, PRINCE2, Agile) High level risk definition(PMBOK, TCM, PRINCE2) Information dissemination(PMBOK) 𝐏𝐡𝐚𝐬𝐞 𝟐: 𝐏𝐥𝐚𝐧𝐧𝐢𝐧𝐠 Focus–Plan in way to facilitate almost real time project progress monitoring, controlling & forecasting Work Breakdown Structure definition (WBS)–(PMBOK, TCM, PRINCE2, Agile) Organization breakdown structure definition(OBS)–(PMBOK, PRINCE2, TCM, Agile) Establishing WBS-OBS linkages (PMBOK, TCM) Resource Breakdown Structure (RBS) – (PMBOK, TCM, Agile) Estimation & Budgeting (PMBOK, TCM, Agile) Cost breakdown structure (PMBOK, TCM) Schedule development (PMBOK, TCM, Agile) Rules of credit (TCM) Interfaces with other systems (Experience) Plan communications (PMBOK, TCM) Quality planning (PMBOK, TCM, PRINCE2) Risk planning (PMBOK, TCM, PRINCE2) Contingency planning (PMBOK, TCM) 𝐏𝐡𝐚𝐬𝐞 𝟑: 𝐄𝐱𝐞𝐜𝐮𝐭𝐢𝐨𝐧 Focus–Collect accurate & timely execution data. Control dynamic incidents Project execution data capture (PMBOK, TCM, Agile, Experience) Change control (PMBOK, TCM, PRINCE2) Quality management (PMBOK, TCM) Risk control (PMBOK, TCM) Contingency management (TCM) Communication (PMBOK, TCM, Agile) 𝐏𝐡𝐚𝐬𝐞 𝟒: 𝐌𝐨𝐧𝐢𝐭𝐨𝐫𝐢𝐧𝐠 & 𝐂𝐨𝐧𝐭𝐫𝐨𝐥𝐥𝐢𝐧𝐠 Focus–Provide almost real time project status information to key stakeholders. Control quickly Planned Value (PMBOK, TCM, Agile) Earned Value (PMBOK, TCM, Agile) Actual Cost (PMBOK, TCM) Variance analysis (PMBOK, TCM, Agile) Forecasting Schedule & Cost (PMBOK, TCM, Agile) Control schedule (PMBOK, TCM) Control costs (PMBOK, TCM) Forensic analysis (TCM) Control quality (PMBOK, TCM) Snag management (TCM, Experience) Risk monitoring (PMBOK, TCM) 𝐏𝐡𝐚𝐬𝐞 𝟓: 𝐂𝐥𝐨𝐬𝐢𝐧𝐠 Focus–Learning, Asset transition Formal closure (PMBOK, TCM) Asset transition (PMBOK, TCM) https://lnkd.in/dridSspp #Sawy_Says
-
🎓Understanding the Complete Work Breakdown Structure (WBS) in Construction Projects 📑When working on a WBS for a construction project, it’s common to see it structured as: 1. Engineering 2. Procurement 3. Construction 📑But in reality, two critical phases are often overlooked—Mobilization(before) and Project Closeout(after). Let’s take a closer look at these essential stages and their Level 2 components: 1. Mobilization 1.1 Site Setup / Site Preparation 1.2 Initial Deliverables 1.3 No Objection Certificate (NOC) from the municipality 2. Engineering 2.1 Shop Drawing Submittal 2.2 Shop Drawing Approval (Executive panels approval) 👉Additionally, engineering should also cover: -Documentation updates -Design updates and approvals -Legal approvals (if required) -Method statement submission and approval -HSE Plan submission and accreditation -Quality Plan submission and approval 3. Procurement 3.1 Prequalification Submittal (requirements & specifications) 3.2 Prequalification Approval 3.3 Material Submittal 3.4 Material Approval 3.5 Purchase Order 3.6 Fabrication & Delivery 4. Construction 4.1 Substructure (excavation, backfilling, etc.) 4.2 Superstructure (structural works) 4.3 Finishing Works 4.4 MEP Works 5. Project Closeout 5.1 Testing 5.2 Consultant Approval 5.3 As-Built Documentation 5.4 Final Handover 👉Key insight: 🏷️When developing a WBS, it’s vital to account for all potential delays, especially those arising from consultant approvals or third-party dependencies. Each approval process should be reflected as a separate activity to mitigate risks and monitor progress effectively. 🏷️By including Mobilization and Project Closeout, you create a more comprehensive, realistic WBS that better reflects the true project lifecycle.
-
✅How to create the most effective WBS for your project: 1. Follow the 100% Rule. The WBS should include 100% of the work required for the project, covering every deliverable, task, and activity. It should not include work that falls outside the project’s scope (i.e., nothing left out, and nothing added). 2. Create Hierarchical Levels. A well-structured WBS has a clear hierarchy that divides the project into increasingly detailed components. The general structure usually has three to four levels: - Level 1: The overall project (the highest-level deliverable or outcome). - Level 2: Major phases or deliverables of the project (e.g., design, implementation, testing, deployment). - Level 3: Sub-deliverables, tasks, or work packages that make up each phase. - Level 4: Further breakdown of smaller tasks or activities, depending on the complexity. 3. Use Clear and Descriptive Naming. Each WBS element should be described in a way that clearly communicates what work is to be done. Avoid vague or generic terms. Use action verbs and nouns that describe specific deliverables and outcomes. 4. Ensure the WBS is Measurable. Each task or work package should be measurable, meaning you can track its progress, completion, or results. This ensures accountability and allows you to monitor the project effectively. 5. Focus on Deliverables, Not Activities. The WBS should emphasize (deliverables) rather than activities. For example, instead of breaking down a task like "Write code," describe the deliverable, such as "Develop software module for feature X." 6. Level of Detail Based on Project Size. The level of detail in your WBS should be appropriate for the complexity of your project. Large, complex projects may require more detailed breakdowns, while simpler projects can have fewer levels. Ensure that the WBS is detailed enough to assign clear responsibilities, yet not overly complex to avoid confusion. 7. Ensure Clear Dependencies. The WBS should outline the dependencies between tasks. This helps in scheduling and resource allocation, and ensures that the project flows logically from one phase to the next. 8. Create Work Packages. At the lowest level of the WBS, break down the project into "work packages" — the smallest units of work that can be easily assigned, scheduled, and tracked. Work packages should have clearly defined start and end points, costs, and responsible team members. 9. Use a Consistent Numbering System. Assign unique identifiers or numbers to each level and component in the WBS (e.g., 1.0 for the main project, 1.1 for a sub-deliverable, 1.1.1 for a work package). This makes it easy to reference tasks in reports and communication. 10. Incorporate Feedback and Adjustments. A WBS should not be static. As the project progresses, or if there are changes in scope, the WBS should be updated. Review it regularly with your team to ensure that it still reflects the project’s current scope and objectives.