Battery Street Tunnel
Filling and sealing the Battery Street Tunnel
Why close the Battery Street Tunnel
With the Alaskan Way Viaduct closed, SR 99 no longer runs through the Battery Street Tunnel. Like the viaduct, the tunnel was built in the 1950s and is seismically vulnerable. Any new or continued use of the tunnel would require prohibitively expensive renovations. Closing the Battery Street Tunnel allows WSDOT to rebuild the three-block stretch of Seventh Avenue North at the tunnel’s north end, improving east-west mobility in that neighborhood.
Scope of work
Work began on Feb. 12, 2019 and is scheduled to be complete in late 2020 or early 2021. The major elements of this work are:
- Decommissioning and removing the tunnel’s utility and mechanical systems.
- Removing hazardous materials from the tunnel.
- Filling the tunnel and sealing its entrances.
- Street restoration along Battery Street, including sidewalk improvements, new curb ramps, street lighting and other pedestrian improvements.
The blue-highlighted zone in the map below shows the work area for the project:
Filling the tunnel (updated December 2019)
In May 2019, the contractor Kiewit began filling the lower half of the Battery Street Tunnel. The fill material is crushed concrete salvaged from the demolition of the viaduct. Trucks poured the crushed concrete through hoppers placed atop grates in Battery Street. Inside the tunnel, vibratory rollers spread and compacted the material in layers.
- First stage of Battery Street Tunnel filling wraps up this summer
- Video: How viaduct rubble is processed for filling the Battery Street Tunnel
- Filling the Battery Street Tunnel from the surface begins next week
Effects of construction
Construction will occur both inside the Battery Street Tunnel and on the surface street above. During construction, neighbors and travelers should expect:
- Traffic lane closures along Battery Street, with a limited number of night and weekend full closures.
- Construction equipment staged at the south end of the tunnel on the west side of First Avenue.
- Temporary building and parking access restrictions according to previously negotiated Temporary Construction Easements.
- Increased truck activity on Battery Street and near the north and south portals.
- Vibration from tunnel filling activities, plus other typical construction effects such as increased dust and noise.
- Local sidewalk access maintained with possible short pedestrian detours.
- Most construction during the daytime, with occasional night work.
- Water misting to reduce dust.
- Occasional temporary closures of cross-street traffic.
- Temporary parking restrictions on Battery Street and side streets for equipment staging.