CN211691716U - Large-span closed stockyard structure for multiple stackers and reclaimers - Google Patents
Large-span closed stockyard structure for multiple stackers and reclaimers Download PDFInfo
- Publication number
- CN211691716U CN211691716U CN201921789466.9U CN201921789466U CN211691716U CN 211691716 U CN211691716 U CN 211691716U CN 201921789466 U CN201921789466 U CN 201921789466U CN 211691716 U CN211691716 U CN 211691716U
- Authority
- CN
- China
- Prior art keywords
- plate
- main beam
- beam body
- main
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型公开一种用于多台堆取料机的超大跨度密闭料场结构,在不改变堆取料机的前提下,对封闭料场进行改进,封闭料场结构牢固,整体成本低;多根桁架柱横向等距布置在料场的中部,每根桁架柱均竖直设置,桁架柱的下端固定设置在预埋基座上,相邻的两根桁架柱的顶部之间通过一根托梁连接,上弦架呈圆弧形结构,上弦架的两端分别固定设置在托梁的两端,托梁的两侧均设置有主拱架,主拱架也呈圆弧形结构,且主拱架的一端固定在托梁上,另一端纵向跨过料场后固定在料场边缘的地面上,主拱架外侧设置有膜材,托梁两侧与上弦架对应两侧以及上弦架顶部和托梁顶部均安装有阳光板;桁架柱和托梁均为H型钢桥结构,且二者结构形式相同。
The utility model discloses a super-span closed material yard structure for multiple stackers and reclaimers. The closed material yard is improved on the premise of not changing the stacker and reclaimer. The closed material yard has a firm structure and low overall cost; A plurality of truss columns are arranged horizontally and equally in the middle of the material yard. Each truss column is arranged vertically. The lower end of the truss column is fixed on the embedded base. The joists are connected, the upper chord is in a circular arc structure, the two ends of the upper chord are respectively fixed on both ends of the joist, both sides of the joist are provided with a main arch, and the main arch is also in a circular arc structure, and One end of the main arch frame is fixed on the joist, and the other end is fixed on the ground at the edge of the material yard after crossing the material yard. Both the top and the top of the joists are equipped with sun panels; the truss columns and the joists are both H-shaped steel bridge structures, and both have the same structural form.
Description
技术领域technical field
本实用新型公开一种用于多台堆取料机的超大跨度密闭料场结构,属于堆取料机技术领域。The utility model discloses a super-span closed material yard structure used for multiple stackers and reclaimers, belonging to the technical field of stackers and reclaimers.
背景技术Background technique
现有机械化料场的混匀料条取料机与相邻一次料场斗轮取料机道床之间的距离较近,空间关系异常紧张。由于设施净距不足,需要对现有设备改造或更换,才能满足封闭建设需求。The distance between the mixing strip reclaimer of the existing mechanized material yard and the track bed of the bucket wheel reclaimer of the adjacent primary material yard is relatively close, and the space relationship is extremely tense. Due to insufficient clear distance of facilities, existing equipment needs to be modified or replaced to meet the needs of closed construction.
共拟定四套封闭方案:A total of four closed plans have been drawn up:
方案一:全缩短斗轮取料机配重方案(五连跨方案);缩短配重侧回转半径,大幅增加配重,上部主体结构相应修改,增加轮组,轨道利旧,封闭大棚立柱高约20m,改造工期约30天/台,该方案中对取料机局部钢结构切割改造。未有先例,配重太短,设备稳定性下降,存在风险。Scheme 1: Fully shorten the counterweight scheme of the bucket wheel reclaimer (five-span scheme); shorten the gyration radius of the counterweight side, greatly increase the counterweight, modify the upper main structure accordingly, increase the wheel set, use the track, and the column height of the closed greenhouse About 20m, the reconstruction period is about 30 days per unit. In this plan, the partial steel structure of the reclaimer is cut and reconstructed. There is no precedent, the counterweight is too short, the stability of the equipment is reduced, and there is a risk.
方案二:不缩短斗轮配重+缩短混匀取料机方案(五连跨方案);与方案一类似,在两两料场之间设置大棚立柱,且立柱为相邻大棚共支柱,与现有封闭大棚一起,形成五连跨,取料机轨距缩短改造,混匀料场贮量损失大。Scheme 2: do not shorten the bucket wheel counterweight + shorten the mixing and reclaimer scheme (five-span scheme); similar to scheme 1, set up a greenhouse column between the two material yards, and the column is a common column of adjacent greenhouses, and Together with the existing closed greenhouses, five continuous spans are formed, the gauge of the reclaimer is shortened, and the storage loss of the mixing yard is large.
方案三:部分缩短斗轮配重+缩短混匀取料机方案(五连跨方案);取料机进行轨距缩短改造。设备改造的台套数最多;混匀料场储量损失较大。Scheme 3: Partially shorten the bucket wheel counterweight + shorten the mixing and reclaimer scheme (five-span scheme); the reclaimer is retrofitted to shorten the gauge. The number of sets of equipment for renovation is the largest; the loss of reserves in the mixing yard is relatively large.
方案四:B3/B4合建为大跨度(四连跨),棚跨度约230m,结构技术难度大。由于跨度非常大,棚顶非常高,但就设备运行净空要求来看,无需如此净空高需求。Option 4: B3/B4 is built together as a large span (four consecutive spans), the span of the shed is about 230m, and the structure is technically difficult. Since the span is very large, the ceiling is very high, but in terms of equipment operating clearance requirements, such a high headroom requirement is not necessary.
实用新型内容Utility model content
本实用新型克服了现有技术存在的不足,提供了一种用于多台堆取料机的超大跨度密闭料场结构,在不改变堆取料机的前提下,对封闭料场进行改进,封闭料场结构牢固,整体成本低。The utility model overcomes the shortcomings of the prior art, provides a super-span closed material yard structure for multiple stackers and reclaimers, and improves the closed material yard without changing the stacker and reclaimer. The closed stockyard has a firm structure and low overall cost.
为了解决上述技术问题,本实用新型采用的技术方案为:用于多台堆取料机的超大跨度密闭料场结构,包括桁架柱、托梁、上弦架和主拱架,多根所述桁架柱横向等距布置在料场的中部,且每根所述桁架柱均竖直设置,其中,所述桁架柱的下端固定设置在预埋基座上,相邻的两根所述桁架柱的顶部之间通过一根托梁连接,所述上弦架呈圆弧形结构,且圆心朝下设置,所述上弦架的两端分别固定设置在托梁的两端,所述托梁的两侧均设置有主拱架,所述主拱架也呈圆弧形结构,且所述主拱架的一端固定在托梁上,所述主拱架的另一端纵向跨过料场后固定在料场边缘的地面上,所述主拱架外侧设置有膜材,所述托梁两侧与上弦架对应两侧以及上弦架顶部和托梁顶部均安装有阳光板;In order to solve the above-mentioned technical problems, the technical scheme adopted by the present invention is as follows: a super-large-span closed material yard structure for multiple stackers and reclaimers, including truss columns, joists, upper chord frames and main arches, a plurality of the trusses The columns are arranged at the same distance in the middle of the material yard, and each of the truss columns is vertically arranged, wherein the lower ends of the truss columns are fixed on the pre-embedded base, and the adjacent two truss columns are arranged vertically. The tops are connected by a joist, the upper chord is in a circular arc structure, and the center of the circle is set downward, the two ends of the upper chord are respectively fixed on the two ends of the joist, and the two sides of the joist are respectively fixed. Both are provided with a main arch frame, which is also in a circular arc structure, and one end of the main arch frame is fixed on the joist, and the other end of the main arch frame crosses the material yard longitudinally and is fixed in the material. On the ground at the edge of the field, the outer side of the main arch frame is provided with a membrane material, and the two sides of the joist and the corresponding sides of the upper chord frame and the top of the upper chord frame and the top of the joist are installed with sun panels;
所述桁架柱和托梁均为H型钢桥结构,且二者结构形式相同,均包括:The truss columns and joists are both H-shaped steel bridge structures, and both have the same structural form, including:
主梁体和横向支撑,多个所述主梁体纵向平行等距设置,相连的所述主梁体之间设置有多个横向支撑;所述主梁体的结构包括主梁本体、连接板、盖板,所述主梁本体和连接板均为H型钢,两个所述主梁本体在竖直面上上下平行设置,多个所述连接板等距设置在两个所述主梁本体之间,所述主梁本体和连接板的宽度相等,所述主梁本体和连接板均纵向分布,使得主梁本体和连接板的水平板能匹配对应,所述主梁本体和连接板在连接部水平板上均对应设置有多个通孔,通过螺栓将主梁本体和连接板连接在一起,所述盖板为包括两种规格的板状结构,两种规格的所述盖板上均规则分布设置有多个通孔,且两种规格的所述盖板单独或组合设置在主梁本体和连接板的连接部水平板上下两侧,所述盖板在主梁本体上矩阵分布并通过螺栓固定在主梁本体和连接板上,两块所述盖板与主梁本体和/或连接板的侧面配合形成一个凹槽型的连接槽;The main beam body and the lateral support, a plurality of the main beam bodies are longitudinally parallel and equidistantly arranged, and a plurality of lateral supports are arranged between the connected main beam bodies; the structure of the main beam body includes a main beam body, a connecting plate, a cover The main girder body and the connecting plate are both H-shaped steel, the two main girder bodies are arranged in parallel up and down on the vertical plane, and a plurality of the connecting plates are arranged equidistantly between the two main girder bodies , the width of the main beam body and the connecting plate are equal, and the main beam body and the connecting plate are distributed longitudinally, so that the horizontal plate of the main beam body and the connecting plate can match and correspond, and the main beam body and the connecting plate are in the connecting part. A plurality of through holes are correspondingly arranged on the horizontal plates, and the main beam body and the connecting plate are connected together by bolts. The cover plate is a plate-like structure including two specifications, and the cover plates of the two specifications are regular A plurality of through holes are distributed, and the cover plates of the two specifications are individually or combined on the upper and lower sides of the horizontal plate of the connecting part of the main beam body and the connecting plate, and the cover plates are distributed in a matrix on the main beam body and pass through. The bolts are fixed on the main beam body and the connecting plate, and the two cover plates cooperate with the sides of the main beam body and/or the connecting plate to form a groove-type connecting groove;
所述横向支撑呈H型钢结构,所述横向支撑的水平板长度小于垂直板的长度,所述横向支撑的两个水平板端部能匹配的插接在主梁本体两个水平板上的连接槽内,同时横向支撑的垂直板对应的匹配顶在主梁本体的垂直板上,且所述横向支撑的水平板上设置的多个通孔与盖板上的通孔相对应,并通过螺栓将横向支撑固定在盖板上;The horizontal support is an H-shaped steel structure, the length of the horizontal plate of the horizontal support is less than the length of the vertical plate, and the ends of the two horizontal plates of the horizontal support can be matched to the connection of the two horizontal plates of the main beam body. In the groove, at the same time, the horizontally supported vertical plates are correspondingly matched against the vertical plates of the main beam body, and the plurality of through holes provided on the horizontally supported horizontal plates correspond to the through holes on the cover plate, and are connected by bolts. Fix the lateral support on the cover;
所述横向支撑的垂直板与主梁本体的垂直板的交汇处匹配设置有角钢,所述角钢的两个侧面上设置有多个通孔,且该通孔与横向支撑的垂直板和主梁本体的垂直板上设置的通孔相对应,并通过螺栓将角钢与横向支撑的垂直板和主梁本体的垂直板固定在一起,所述角钢的两个侧板内侧水平设置有连接支撑板,所述连接支撑板与角钢一体成型,所述连接支撑板上设置有通孔,且处于同一水平面内对角线位置的两个连接支撑板之间通过螺栓连接有连接杆。The intersection of the vertical plate of the horizontal support and the vertical plate of the main beam body is matched with an angle steel, and two sides of the angle steel are provided with a plurality of through holes, and the through holes are matched with the vertical plate and the main beam of the horizontal support. The through holes provided on the vertical plate of the main body correspond to each other, and the angle steel, the vertical plate of the horizontal support and the vertical plate of the main beam body are fixed together by bolts, and the inner side of the two side plates of the angle steel are horizontally provided with connecting support plates, The connecting support plate and the angle steel are integrally formed, the connecting support plate is provided with a through hole, and a connecting rod is connected by bolts between the two connecting support plates at the diagonal position in the same horizontal plane.
所述主梁本体的两个水平板之间匹配的设置有加强板,所述加强板垂直与主梁本体的垂直板设置,并与主梁本体的垂直板焊接固定在一起。A reinforcing plate is matched between the two horizontal plates of the main beam body, the reinforcing plate is vertically arranged with the vertical plate of the main beam body, and is welded and fixed with the vertical plate of the main beam body.
所述横向支撑的垂直板端部上下侧均设置有台阶,所述台阶的高度与盖板的厚度相等,使得所述台阶与横向支撑的水平板配合形成的卡槽匹配的插接在盖板上。The upper and lower sides of the vertical plate end of the horizontal support are provided with steps, and the height of the steps is equal to the thickness of the cover plate, so that the steps and the horizontal plates of the horizontal support are matched with the card grooves to be inserted into the cover plate. superior.
所述上弦架和主拱架均为桁架式结构,由弧形主杆及连接支杆和/或斜拉杆通过螺栓和/或焊接而成。The upper chord frame and the main arch frame are both truss-type structures, which are formed by bolts and/or welding of arc-shaped main rods, connecting struts and/or diagonal tie rods.
所述托梁、上弦架和阳光板之间配合形成一个腔室,且在阳光板对应位置安装门窗即可形成用于指挥堆取料机工作的控制室或临时休息室。The joist, the upper string frame and the sun panel cooperate to form a chamber, and installing doors and windows at the corresponding positions of the sun panel can form a control room or a temporary rest room for directing the stacker-reclaimer to work.
本实用新型与现有技术相比具有的有益效果是:本实用新型在不改变堆取料机的前提下,对封闭料场进行改进,封闭料场结构牢固,整体成本低,而且本实用新型可以实现现场钢桥的全装配化和全螺栓连接,让施工现场做到零焊接或减少焊接;与传统结构形式相比,本实用新型质量更为可靠;本实用新型的施工速度快,将以往动辄数年的工期降低到数月;更加快速的施工速度可以显著降低企业成本,增加企业的社会效益。Compared with the prior art, the utility model has the beneficial effects as follows: the utility model improves the closed material yard under the premise of not changing the stacker and reclaimer, the closed material yard has a firm structure, and the overall cost is low, and the utility model It can realize the full assembly and full bolt connection of the on-site steel bridge, so that the construction site can achieve zero welding or reduce welding; compared with the traditional structural form, the quality of the utility model is more reliable; the construction speed of the utility model is fast, and the previous The construction period of several years is reduced to several months; the faster construction speed can significantly reduce the cost of the enterprise and increase the social benefit of the enterprise.
附图说明Description of drawings
下面结合附图对本实用新型做进一步的说明。The utility model will be further described below in conjunction with the accompanying drawings.
图1为本实用新型的结构示意图。Figure 1 is a schematic structural diagram of the utility model.
图2为本实用新型中堆取料机在料场内移动示意图。FIG. 2 is a schematic diagram of the movement of the stacker-reclaimer in the material yard in the utility model.
图3为本实用新型中桁架柱或托梁的结构示意图。3 is a schematic structural diagram of a truss column or a joist in the utility model.
图4为图3中主梁体的结构示意图。FIG. 4 is a schematic structural diagram of the main beam body in FIG. 3 .
图5为图3中横向支撑的示意图。FIG. 5 is a schematic diagram of the lateral support in FIG. 3 .
图6为图3中支撑与主梁体的连接示意图。FIG. 6 is a schematic diagram of the connection between the support and the main beam in FIG. 3 .
图中:1为桁架柱、11为主梁体、111为主梁本体、112为连接板、113为盖板、114为连接槽、12为横向支撑、13为角钢、14为连接支撑板、15为连接杆、16为加强板、17为台阶、2为托梁、3为上弦架、4为主拱架。In the figure: 1 is the truss column, 11 is the main beam body, 111 is the main beam body, 112 is the connecting plate, 113 is the cover plate, 114 is the connecting groove, 12 is the lateral support, 13 is the angle steel, 14 is the connecting support plate, 15 is the connecting rod, 16 is the reinforcing plate, 17 is the step, 2 is the joist, 3 is the upper string frame, and 4 is the main arch frame.
具体实施方式Detailed ways
如图1、图3~图6所示,本实用新型用于多台堆取料机的超大跨度密闭料场结构,包括桁架柱1、托梁2、上弦架3和主拱架4,多根所述桁架柱1横向等距布置在料场的中部,且每根所述桁架柱1均竖直设置,其中,所述桁架柱1的下端固定设置在预埋基座上,相邻的两根所述桁架柱1的顶部之间通过一根托梁2连接,所述上弦架3呈圆弧形结构,且圆心朝下设置,所述上弦架3的两端分别固定设置在托梁2的两端,所述托梁2的两侧均设置有主拱架4,所述主拱架4也呈圆弧形结构,且所述主拱架4的一端固定在托梁2上,所述主拱架4的另一端纵向跨过料场后固定在料场边缘的地面上,所述主拱架4外侧设置有膜材,所述托梁2两侧与上弦架3对应两侧以及上弦架3顶部和托梁2顶部均安装有阳光板;主拱架4的前后侧可以采用和现有技术一样的方式进行封堵。As shown in Figure 1, Figure 3 to Figure 6, the utility model is used for the super-span closed material yard structure of multiple stackers and reclaimers, including a truss column 1, a
所述桁架柱1和托梁2均为H型钢桥结构,且二者结构形式相同,均包括:The truss column 1 and the
主梁体11和横向支撑12,多个所述主梁体11纵向平行等距设置,相连的所述主梁体11之间设置有多个横向支撑12;所述主梁体11的结构包括主梁本体111、连接板112、盖板113,所述主梁本体111和连接板112均为H型钢,两个所述主梁本体111在竖直面上上下平行设置,多个所述连接板112等距设置在两个所述主梁本体111之间,所述主梁本体111和连接板112的宽度相等,所述主梁本体111和连接板112均纵向分布,使得主梁本体111和连接板112的水平板能匹配对应,所述主梁本体111和连接板112在连接部水平板上均对应设置有多个通孔,通过螺栓将主梁本体111和连接板112连接在一起,所述盖板113为包括两种规格的板状结构,两种规格的所述盖板113上均规则分布设置有多个通孔,且两种规格的所述盖板113单独或组合设置在主梁本体111和连接板112的连接部水平板上下两侧,所述盖板113在主梁本体111上矩阵分布并通过螺栓固定在主梁本体111和连接板112上,两块所述盖板113与主梁本体111和/或连接板112的侧面配合形成一个凹槽型的连接槽114;The
所述横向支撑12呈H型钢结构,所述横向支撑12的水平板长度小于垂直板的长度,所述横向支撑12的两个水平板端部能匹配的插接在主梁本体111两个水平板上的连接槽114内,同时横向支撑12的垂直板对应的匹配顶在主梁本体111的垂直板上,且所述横向支撑12的水平板上设置的多个通孔与盖板113上的通孔相对应,并通过螺栓将横向支撑12固定在盖板113上;The
所述横向支撑12的垂直板与主梁本体111的垂直板的交汇处匹配设置有角钢13,所述角钢13的两个侧面上设置有多个通孔,且该通孔与横向支撑12的垂直板和主梁本体111的垂直板上设置的通孔相对应,并通过螺栓将角钢13与横向支撑12的垂直板和主梁本体111的垂直板固定在一起,所述角钢13的两个侧板内侧水平设置有连接支撑板14,所述连接支撑板14与角钢13一体成型,所述连接支撑板14上设置有通孔,且处于同一水平面内对角线位置的两个连接支撑板14之间通过螺栓连接有连接杆15。The intersection of the vertical plate of the
所述主梁本体111的两个水平板之间匹配的设置有加强板16,所述加强板16垂直与主梁本体111的垂直板设置,并与主梁本体111的垂直板焊接固定在一起。A reinforcing
所述横向支撑12的垂直板端部上下侧均设置有台阶17,所述台阶17的高度与盖板113的厚度相等,使得所述台阶17与横向支撑12的水平板配合形成的卡槽匹配的插接在盖板113上。The upper and lower sides of the vertical plate end of the
所述上弦架3和主拱架4均为桁架式结构,由弧形主杆及连接支杆和/或斜拉杆通过螺栓和/或焊接而成,为常规的桁架结构技术。The upper chord frame 3 and the main arch frame 4 are both truss-type structures, which are formed by bolts and/or welding of arc-shaped main rods and connecting struts and/or diagonal tie rods, which are conventional truss structure technologies.
所述托梁2、上弦架3和阳光板之间配合形成一个腔室,且在阳光板对应位置安装门窗即可形成用于指挥堆取料机工作的控制室或临时休息室。The
本实用新型涉及的一种用于多台堆取料机的超大跨度密闭料场结构的施工方法,按以下步骤实施:The utility model relates to a construction method for a super-large-span closed material yard structure for multiple stackers and reclaimers, which is implemented according to the following steps:
第一步:沿料场中部横向以及绕料场边缘选择适当位置预埋基座;The first step: select the appropriate position to embed the base along the transverse direction of the middle of the yard and the edge of the winding yard;
第二步:将组装好的桁架柱1竖直固定在料场中部;然后将组装好的托梁2和上弦架3通过焊接和/或螺栓连接固定在一起;Step 2: Fix the assembled truss column 1 vertically in the middle of the stockyard; then fix the assembled
第三步:将固定在一起的托梁2和上弦架3依次吊装到相邻的两个桁架柱1顶部固定;The third step: hoist the fixed
第四步:将组装好的主拱架4依次吊装固定在托梁2两侧,且所述主拱架4的一端固定在托梁2上,所述主拱架4的另一端纵向跨过料场后固定在料场边缘的地面上;The fourth step: the assembled main arch 4 is hoisted and fixed on both sides of the
第五步:在所述主拱架4外侧固定有膜材,在所述托梁2两侧与上弦架3对应两侧以及上弦架3顶部和托梁2顶部均安装有阳光板,完成安装。The fifth step: a membrane material is fixed on the outer side of the main arch 4, and a solar panel is installed on both sides of the
所述桁架柱1和托梁2均为H型钢桥结构,且二者组装方法均相同,具体如下:The truss column 1 and the
第一步,工厂准备阶段;The first step, the factory preparation stage;
根据设计尺寸制作对应的零部件,并将多个加强板16等间距焊接在主梁本体111的一侧垂直板上备用,将连接支撑板14焊接在角钢13两个侧板的内侧备用;将横向支撑12的垂直板两端端部上下侧加工台阶17备用;Corresponding parts are produced according to the design size, and a plurality of reinforcing
第二步,工厂预组合;The second step, factory pre-assembly;
将两个主梁本体111之间通过螺栓固定设置有多个等间距分布的连接板112,并在连接板112所在位置的主梁本体111水平板两侧上下位置均通过螺栓固定设置盖板113,形成主梁体11;A plurality of equally spaced connecting
第三步,实际安装场所正式组合;The third step, the actual installation site is formally combined;
a.将多个主梁体11平行排布,并在相邻的两个主梁体11之间设置多个横向支撑12,每个横向支撑12的两端均与对应的盖板113用螺栓连接在一起;a. Arrange a plurality of
b.将横向支撑12与主梁体11的交汇处设置角钢13,并将角钢13通过螺栓连接固定在横向支撑12与主梁体11上;b. Set the
c.在由横向支撑12与主梁体11围成的框体内,用连接杆15将对角线上的两个角钢13用螺栓连接在一起。c. In the frame enclosed by the
所述连接杆15的两端均对应连接支撑板14设置有连接通孔,且在每个由横向支撑12与主梁体11围成的框体内,一个连接杆15固定在连接支撑板14的上侧,另一个连接杆15固定在对应对角线连接支撑板14的下侧。Both ends of the connecting
所述连接杆15为角钢结构。The connecting
堆取料机工作流程:如图2所示,悬臂式斗轮堆取料机采用断续行走+断续旋转的作业方式。堆取料机从料场边缘开始工作,起点在如图所示A点位置,沿行走轨道由①轴往⑤轴方向移动,堆取料机上安有脉冲计米器,堆取料机上部回转机构沿图中箭头1方向旋转,堆取料机在移动至B点前可随意旋转堆取料,当移动到B点位置时,脉冲计米器记录下所行走距离达到预先设定米数,此时,堆取料机行走机构停止前进,上部回转机构沿如图所示箭头2方向旋转至图中所示位置,然后行走机构开始往前移动,当移动到C位置时,上部回转机构可按图中所示箭头3、4方向旋转也可反方向旋转。The working process of the stacker and reclaimer: As shown in Figure 2, the cantilever bucket wheel stacker and reclaimer adopts the operation mode of intermittent walking + intermittent rotation. The stacker and reclaimer starts working from the edge of the material yard, starting at point A as shown in the figure, and moves along the walking track from the ① axis to the ⑤ axis direction. The mechanism rotates in the direction of arrow 1 in the figure. The stacker and reclaimer can rotate the stacker and reclaimer at will before moving to point B. When moving to point B, the pulse meter recorder records that the distance traveled reaches the preset number of meters. At this time, the walking mechanism of the stacker-reclaimer stops moving forward, and the upper slewing mechanism rotates along the direction of
本实用新型涉及的料场封闭改造原则是在保证料场功能不变前提下,在线不停产改造。机械化料场封闭包括8个料条封闭、堆取设备改造等。封闭基本方案是上部为钢结构、下部为混凝土短柱,封闭厂房短柱采用桩基,屋面封闭采用膜材料。本实用新型还涉及配电、照明、防雷设施及电讯系统的改造。以及屋面雨水集排系统、雨水收集及预处理设施及配套的闸门、泵站、水泵等。还有消防器材的配备(配备灭火器),以及现有建(构)筑物的拆除及还建。The principle of the closed transformation of the material yard involved in the utility model is that on the premise that the function of the material yard remains unchanged, the online production will not be transformed. The closure of the mechanized material yard includes the closure of 8 material strips and the transformation of stacking equipment. The basic scheme of closure is that the upper part is steel structure, the lower part is concrete short column, the short column of the closed workshop adopts pile foundation, and the roof is closed using membrane material. The utility model also relates to the transformation of power distribution, lighting, lightning protection facilities and telecommunication systems. And roof rainwater collection and drainage system, rainwater collection and pretreatment facilities and supporting gates, pump stations, water pumps, etc. There are also the provision of fire-fighting equipment (with fire extinguishers), as well as the demolition and restoration of existing buildings (structures).
下面结合具体实施例对本实用新型进行进一步的阐述。The present utility model will be further elaborated below in conjunction with specific embodiments.
本实用新型涉及的的H型钢桥结构,包括纵向类蜂窝式多层H型钢主梁、实腹式H型横向支撑、实腹式角钢斜支撑,其中纵向类蜂窝式多层H型钢主梁为新型组合形式,即纵向类蜂窝式多层H型钢主梁包括最上层、最下层连续的H型钢和中间一层或多层根据一定规则或受力特性而隔一定间距排列的H型钢组成;最上层和最下层H型钢使用同规格;类蜂窝式多层H型钢主梁按一定间距设置形成纵向主要受力框架;H型钢间的连接采用全螺栓连接,满足装配式的要求。The H-shaped steel bridge structure involved in the utility model comprises a longitudinal honeycomb-type multi-layer H-shaped steel main girder, a solid-web H-shaped transverse support, and a solid-web angle steel diagonal support, wherein the longitudinal honeycomb-type multi-layer H-shaped steel main girder is The new combination form, that is, the longitudinal honeycomb-type multi-layer H-beam main beam includes the uppermost and lowermost continuous H-beams and the middle layer or layers of H-beams arranged at certain intervals according to certain rules or stress characteristics; the most The upper and lowermost H-beams use the same specifications; the honeycomb-like multi-layer H-beam main beams are arranged at certain intervals to form the longitudinal main stress frame; the connection between the H-beams adopts full bolt connection to meet the requirements of assembly.
实腹式H型横向支撑采用腹板延长至主梁腹板处插入式连接,腹板间用角钢螺栓连接;翼缘采用盖板连接,为了保证下盖板的整体,将横向支撑腹板打断,以满足盖板的空间要求;The solid-web type H-shaped lateral support adopts the web extension to the main girder web plate for plug-in connection, and the webs are connected by angle steel bolts; the flanges are connected by cover plates. to meet the space requirements of the cover;
其中,实腹式H型横向支撑与其所连纵向结构相同规格,即与最上层或最下层连接的横向支撑与其采用同规格,与中间层连接的横向支撑与中间层采用相同规格。Among them, the solid belly type H-shaped transverse support has the same specifications as the longitudinal structure it is connected to, that is, the transverse support connected to the uppermost or lowermost layer adopts the same specification, and the transverse support connected to the middle layer adopts the same specification as the middle layer.
直接在工厂焊接横板在角钢上以连接斜支撑。Weld the cross plate directly on the angle steel at the factory to connect the diagonal bracing.
采用上述连接方式以及在主梁对应位置添加加劲肋以满足横向支撑刚性要求。The above connection method and the addition of stiffeners at the corresponding positions of the main beams are used to meet the rigidity requirements of lateral support.
横向支撑设置在中间层H型钢的中心位置,以满足结构稳定性和美观功能。The lateral support is set at the center of the H-beam in the middle layer to meet the structural stability and aesthetic function.
本实用新型涉及H型钢桥结构的装配方法,首先将类蜂窝式多层H型钢主梁组合安装,翼缘用螺栓连接;再将类蜂窝式多层H型钢主梁按一定间距设置形成纵向主要受力框架;然后将实腹式H型钢横向支撑放到指定位置,进行盖板连接;再将角钢与腹板连接;同理进行下一根主梁与横向支撑的连接;最后将斜支撑连接到角钢上,上述连接全部采用高强螺栓。The utility model relates to an assembling method of an H-shaped steel bridge structure. First, a honeycomb-like multi-layer H-shaped steel main beam is assembled and installed, and flanges are connected with bolts; Stress-bearing frame; then place the solid-web H-beam lateral support at the designated position to connect the cover plate; then connect the angle steel to the web; similarly, connect the next main beam and the lateral support; finally, connect the diagonal support To the angle steel, all the above connections are made of high-strength bolts.
本实用新型按下述方式施工:The utility model is constructed in the following manner:
1、材料进场后,开始组装跨中的桁架柱,首先将进场的H型钢用等强连接板进行拼接,拼接成四段相同的钢柱,拼接完成后分别连接两段H钢柱之间的H钢梁,然后将两排钢架用同样钢梁连接,使之形成柱状结构。随后在两对角H钢之间连接斜撑(圆管)。将高强螺栓全部终拧。1. After the materials enter the site, start to assemble the truss columns in the middle of the span. First, the incoming H-beams are spliced with equal-strength connecting plates, and spliced into four identical steel columns. After the splicing is completed, the two H steel columns are respectively connected. The H steel beams between the two rows of steel frames are then connected with the same steel beams to form a columnar structure. Then connect the diagonal braces (round tubes) between the two diagonal H steels. Tighten all the high-strength bolts.
2、组装完成后,用吊车将桁架柱吊起,吊点位于柱顶端,起吊前先进行试吊,待结构稳定后开始起吊,起吊至H钢底端柱脚板孔与预埋螺栓完全对上,然后缓慢下落至底,加楔铁找平后将螺母终拧,最后进行二次浇筑。2. After the assembly is completed, use a crane to hoist the truss column. The lifting point is at the top of the column. Before hoisting, carry out a trial hoisting. After the structure is stable, start hoisting. Hoist it until the bottom of the H-steel end column foot plate hole and the embedded bolt are completely on top , and then slowly drop to the bottom, add a wedge iron to level the nut, and finally screw the nut, and finally carry out the secondary pouring.
3、用同样方法将50米间距的另一桁架柱固定在基础上。3. Fix another truss column with a distance of 50 meters to the foundation in the same way.
4、两个桁架柱都安装完毕后,开始进行托梁的组装。首先组装下弦平面结构,分别将多段H型钢用法兰等强拼接成两个长弦杆,按图纸将两弦杆用垂杆(H型钢)连接,垂杆之间连接上斜杆(H型钢),将螺栓全部终拧。4. After the two truss columns are installed, start the assembly of the joists. First assemble the lower chord plane structure, respectively splicing the multi-section H-beams into two long chords with equal strength with flanges, connect the two chords with vertical rods (H-beams) according to the drawing, and connect the upper inclined rods (H-beams) between the vertical rods. , and tighten all the bolts.
5、上弦部分组装,分别将多段圆管按图纸用法兰等强拼接成两个弧状弦杆,用吊车将两弦杆立起,用水准仪把两弦杆调平,并使用钢尺测量两弦杆的弦长和拱高是否与图纸尺寸相吻合或偏差在规范允许范围内。然后进行圆管的组装,圆管组装顺序宜从中间向两侧对称组装。将两弦杆连接成网架型结构。完成后用水准仪将上弦结构调平。5. Assemble the upper chord, respectively splicing the multi-section circular tubes into two arc-shaped chords according to the drawings with equal strength of flanges, erect the two chords with a crane, level the two chords with a level, and measure the two chords with a steel ruler Whether the chord length and arch height of the rod are consistent with the drawing size or the deviation is within the allowable range of the specification. Then the round tube is assembled, and the round tube assembly sequence should be symmetrically assembled from the middle to the two sides. Connect the two chords into a grid-like structure. Use a level to level the winding structure when finished.
6、上弦结构安装好后,将下弦结构平放到地面,用水准仪调平,然后用吊车将上弦结构吊至下弦结构正上方,缓慢下落,直至完全落至下弦结构上,用高强螺栓初拧上,随后按照图纸将上下弦结构用圆管连接起来,圆管通过高强螺栓和连接板完成连接,组装成稳定的桁架托梁结构。6. After the upper chord structure is installed, place the lower chord structure flat on the ground, level it with a level, then use a crane to hoist the upper chord structure to just above the lower chord structure, slowly drop it until it completely falls on the lower chord structure, and use high-strength bolts for initial tightening. Then, according to the drawings, the upper and lower chord structures are connected with circular tubes. The circular tubes are connected by high-strength bolts and connecting plates, and assembled into a stable truss joist structure.
7、桁架托梁组装好后,进行下一步,将托梁吊至两桁架柱上。具体步骤如下:用两台相同型号吊车,吊点在托梁上弦杆(具体计算得知),起吊前进行试吊,待托梁结构稳定后开始起吊,两台吊车相互配合将托梁吊至桁架柱顶端,用高强螺栓将其与桁架柱固定后撤离吊车。7. After the truss joists are assembled, go to the next step and hoist the joists to the two truss columns. The specific steps are as follows: use two cranes of the same model, the lifting point is on the chord of the joist (the specific calculation is known), carry out trial lifting before lifting, and start lifting after the structure of the joist is stable, and the two cranes cooperate with each other to lift the joist to At the top of the truss column, use high-strength bolts to fix it with the truss column and evacuate the crane.
8、将料场按长度方向以50米间距为一个单元组装成上述托梁结构。8. Assemble the stock yard as a unit with a distance of 50 meters in the length direction to form the above-mentioned joist structure.
9、桁架托梁结构完成后开始进行主拱架的安装;9. After the truss joist structure is completed, start the installation of the main arch;
(1)把主钢梁按图纸顺序在地面摆放整齐;使用水准仪找平地胎。摆放钢梁至地胎上,确定位置大致几何尺寸后,检查等强拼接板及钢梁拼接位置处摩擦面是否符合安装要求,高强螺栓规格是否符合;(1) Arrange the main steel beams neatly on the ground in the order of the drawings; use a level to level the tires. Place the steel beam on the ground tire, and after determining the approximate geometric size of the position, check whether the friction surface of the equal-strength splicing plate and the splicing position of the steel beam meets the installation requirements, and whether the high-strength bolts meet the specifications;
(2)用等强连接板把各段梁进行连接,把所有螺栓都初拧上,初拧程度按规范及公司技术要求进行;(2) Connect each section of beam with equal-strength connecting plate, and initially screw all bolts.
(3)用水准仪把半跨梁调平,并使用钢尺测量半跨梁组成的拼装单元弦长和拱高是否与图纸尺寸相吻合或偏差在规范允许范围内;(3) Use a level to level the half-span beam, and use a steel ruler to measure whether the chord length and arch height of the assembled unit composed of the half-span beam are consistent with the size of the drawing or the deviation is within the allowable range of the specification;
(4)把半跨梁调平,尺寸测量完好后,把所有螺栓全部终拧,终拧程度按规范及公司技术要求进行;(4) After the half-span beam is leveled and the dimensions are measured in good condition, all the bolts are finally screwed, and the final screwing degree is carried out according to the specifications and the company's technical requirements;
(5)把拼好的两半跨梁使用相同吨位的吊车起吊,连接刚性系杆、水平支撑形成稳定的吊装单元,次结构螺栓连接应按规范及公司技术要求进行先初拧后终拧,终拧程度按规范及公司技术要求进行;使用临时支撑固定吊装单元。拱形钢结构的组装顺序宜从中间向两侧对称组装。拱形钢结构在组装过程中应及时连接侧向稳定构件,或采用缆风绳等临时施工措施,以确保吊装单元的稳定性。拱形钢结构的安装是一个由构件、机构、不稳定结构向稳定结构的施工过程,因此在安装过程中必须十分重视构件及吊装单元的稳定性,应采取设置临时支撑、拉设缆风绳、临时加固等措施确保吊装单元的稳定。(5) Lift the assembled two half-span beams with cranes of the same tonnage, and connect rigid tie rods and horizontal supports to form a stable hoisting unit. The bolted connection of the secondary structure should be initially screwed first and then finally screwed according to the specifications and the company's technical requirements. The final screwing degree is carried out according to the specifications and the company's technical requirements; use temporary supports to fix the hoisting unit. The assembly sequence of the arched steel structure should be symmetrically assembled from the middle to the two sides. During the assembly process of the arched steel structure, the lateral stabilizing members should be connected in time, or temporary construction measures such as cables and wind ropes should be adopted to ensure the stability of the hoisting unit. The installation of the arched steel structure is a construction process from components, mechanisms, and unstable structures to stable structures. Therefore, during the installation process, great attention must be paid to the stability of components and hoisting units. Temporary supports and cable wind ropes should be set up. , temporary reinforcement and other measures to ensure the stability of the hoisting unit.
10、吊装;10. Hoisting;
(1)在吊装前先进行试吊,选择好吊点,保证各接点位置的统一以有利于钢梁的平衡。在梁的两端系两根缆风绳,防止梁在起吊过程中晃动,如有晃动可以通过对两端的绳子施加力来调节。准备工作就绪后开始进行试吊。在构件离地面1m左右时停吊,静吊5分钟,检查各连接点是否安全、拱梁是否平衡。如采用绑扎方法进行吊装时,发现绑扎点位置不正确后将拱梁吊回地面拼接台,用撑子把拱梁固定好防止倾倒,根据拱梁在空中倾斜的方向在原绑扎点位置附近重新选择绑扎点,注意移动的位置不宜过大,按上述过程重新操作一次再进行试吊,直到拱梁在空中位置平衡为止。记下此时两个绑扎点的准确位置,再进行下一榀拱梁吊装时按该位置进行吊装;(1) Carry out a trial hoisting before hoisting, select a good hoisting point, and ensure the unity of the position of each joint to facilitate the balance of the steel beam. Two cable wind ropes are tied at both ends of the beam to prevent the beam from shaking during the lifting process. If there is shaking, it can be adjusted by applying force to the ropes at both ends. After the preparations are ready, start the test lift. Stop the hoisting when the component is about 1m from the ground, and hoist it statically for 5 minutes to check whether each connection point is safe and whether the arch beam is balanced. If the lashing method is used for hoisting, if it is found that the position of the lashing point is incorrect, the arch beam will be hoisted back to the ground splicing platform, and the arch beam will be fixed with a brace to prevent it from tipping. Binding point, pay attention to the moving position should not be too large, repeat the above process and then carry out trial lifting until the arch beam is balanced in the air. Note down the exact position of the two binding points at this time, and then hoist the next arch beam according to this position;
(2)把钢梁柱底和拱顶同时提高一米左右,等钢拱架提升后成为稳定的吊装单元后再提高钢拱架柱脚部位至柱子的顶部位置;法兰部位继续提升至理论高度;(2) Raise the bottom of the steel beam and the column and the vault by about one meter at the same time. After the steel arch is raised to become a stable hoisting unit, raise the column foot of the steel arch to the top of the column; the flange continues to be raised to the theoretical level. high;
(3)拱顶不动,慢慢提高柱脚部位使柱脚板的锚栓孔对上预埋锚栓;然后使用柱脚螺母进行拱架初步调平;(3) The vault does not move, slowly raise the column foot part so that the anchor bolt hole of the column foot plate is aligned with the pre-embedded anchor bolt; then use the column foot nut to initially level the arch;
(4)吊车用同样的办法把对应的吊装单元吊装到位,此吊装单元需将柱脚板固定在桁架托梁的下弦结构上,对钢拱架进行锚栓初步调平。其法兰部位要高于相对的吊装单元法兰位置;(4) The crane uses the same method to hoist the corresponding hoisting unit in place. This hoisting unit needs to fix the column foot plate on the lower chord structure of the truss joist, and perform the preliminary leveling of the anchor bolt on the steel arch. Its flange position is higher than the flange position of the opposite hoisting unit;
(5)两个吊装单元的拱顶吊车,相互配法兰合拢到位,进行人工高空操作;构件在吊装过程中应控制其变形,特别要注意不得产生永久性变形;(5) The vault cranes of the two hoisting units are matched with each other and the flanges are closed in place to perform artificial high-altitude operations; the deformation of the components should be controlled during the hoisting process, and special attention should be paid to not cause permanent deformation;
(6)登高工人把安全带和工具包带好,挂上自锁器,利用吊车提升吊拦携人及工具器械到拱顶法兰板的位置,锁好螺栓,对螺栓紧固。登高工人高空作业时用自锁器来保证自身安全,安全到达地面才能去掉自锁器上的安全扣。拱顶对接时工人必须带好工具包,把工具和螺丝放在工具包内,把安全绳系在生命线上。螺栓终拧完毕后,在节点处用油漆进行标记处理。(6) Climbing workers wear safety belts and tool bags, hang up the self-locking device, use a crane to lift the hoist and carry people and tools to the position of the flange plate of the vault, lock the bolts, and fasten the bolts. Climbing workers use the self-locking device to ensure their own safety when working at high altitudes, and only when they reach the ground can they remove the safety buckle on the self-locking device. When the vault is docked, the worker must bring the tool kit, put the tools and screws in the tool kit, and tie the safety line to the lifeline. After the bolts are finally screwed, the joints are marked with paint.
11、膜材安装;11. Membrane installation;
(1)在现场打开包装前,应先确定膜单元的准确安装位置。膜单元展开时,应采取必要的措施防止膜材受到污染或损伤。展开和吊装膜单元时可使用临时夹板,但安装过程中应避免膜单元与临时夹板连接处产生撕裂。清理现场,对可能伤及膜材的物件应进行安全防护。安装前应该对支撑结构及钢构件进行复测,以确认满足膜安装要求;(1) Before opening the package on site, the exact installation position of the membrane unit should be determined. When the membrane unit is unfolded, necessary measures should be taken to prevent the membrane material from being polluted or damaged. Temporary splints can be used when unfolding and hoisting the membrane unit, but during the installation process, tearing of the connection between the membrane unit and the temporary splint should be avoided. Clean up the site, and protect the objects that may damage the membrane material. Before installation, the support structure and steel members should be re-tested to confirm that the membrane installation requirements are met;
(2)用卷扬机拖拽膜材时注意卡具的牢靠,拖拽全程要密切观察,防止挂烂和划伤。膜材横向拉伸率要保证在3.3%。膜单元宜连续安装就位。当不能连续安装就位时,应采取可靠的临时固定措施。当风力达到四级或气温低于4℃时,不宜进行膜单元安装;当风力达到五级及以上时,严禁进行膜单元安装。铝条安装要在一条直线,跨度方向自攻钉间距为70mm,自攻钉位置要在铝条中间,成一条直线(不能是曲线),自攻钉间距要保持一致,拉出的膜材边要与铝条边保持一致(即为直线,不能是曲线)。膜结构安装完毕后,应对膜体内、外表面进行清洁;(2) Pay attention to the firmness of the clamp when pulling the membrane material with the hoist, and observe closely the whole process of dragging to prevent rotting and scratching. The transverse stretch rate of the film should be guaranteed to be 3.3%. Membrane units should be installed continuously in place. When it cannot be installed in place continuously, reliable temporary fixing measures should be taken. When the wind power reaches level 4 or the temperature is lower than 4°C, it is not suitable to install the membrane unit; when the wind force reaches
(3)在桁架托梁上弦拱顶处安装阳光板,在打自攻丝前也要先打铝条。(3) Install solar panels at the top chord vaults of truss joists, and punch aluminum strips before self-tapping.
12、山墙板安装;12. Gable board installation;
(1)对山墙构件复测数据的分析,检查山墙构件尺寸是否正确,避免起吊后无法安装;(1) Analysis of the re-measurement data of the gable components, check whether the size of the gable components is correct, and avoid installation after lifting;
(2)用单点红外线测量仪放出轴线,确定水平梁位置,在山墙基础预埋扳上作出水平梁两条边线的位置,焊接限位板。注意水平梁外面与H型钢上面的防尘网连接板齐平;(2) Use a single-point infrared measuring instrument to release the axis, determine the position of the horizontal beam, make the position of the two sides of the horizontal beam on the pre-embedded plate of the gable foundation, and weld the limit plate. Note that the outside of the horizontal beam is flush with the air filter connecting plate on the H-beam;
(3)起吊抗风梁时,一台吊车位于轴线外侧,吊点位于抗风梁顶端偏下,另一吊车钩用吊篮吊人,连接抗风梁与钢拱架(螺栓连接),顶端固定好后,地面施工人员需在脚手架平台进行抗风梁底端与水平梁的连接(螺栓连接),特别注意测量抗风梁两个方向的垂直度;(3) When lifting the wind-resistant beam, one crane is located on the outside of the axis, the lifting point is located below the top of the wind-resistant beam, and the other crane hook is used to hang people with a gondola, connecting the wind-resistant beam and the steel arch (bolt connection), and the top After fixing, the ground construction personnel need to connect the bottom end of the wind-resistant beam to the horizontal beam (bolt connection) on the scaffolding platform, and pay special attention to measuring the verticality of the wind-resistant beam in both directions;
(4)防尘网安装使用吊车吊篮安装,从下往上安装,先安装中间再左右完成打板。确定尺寸需要用蓝外线或者透明水平管,尺寸控制主要考虑垂直线和水平线,同时考虑色带的对接缝。水平方向两块防尘网需要校准一次水平误差;(4) The dust-proof net is installed using a crane and hanging basket, and is installed from the bottom to the top. Install the middle first and then complete the left and right panels. To determine the size, it is necessary to use a blue outer line or a transparent horizontal tube. The size control mainly considers the vertical line and the horizontal line, and also considers the seam of the ribbon. The two dust filters in the horizontal direction need to calibrate the horizontal error once;
(5)防尘网搭接要有规律,不能出现混乱的搭接局面,左右搭接30毫米以下,上下搭接不超过5毫米,超过4.5米的板材要在2.25米处加垫片,垫片为专用垫片,8毫米的螺栓。打自攻丝前应先打铝条,自攻丝保证横平竖直,完成一个马上盖帽,如果质量不好的塑料帽要用结构胶粘牢。检查防尘网的污染情况并马上处理。钢拱架处的防尘网用角磨机将多余部分切除,切除断面用白色油漆进行补漆;(5) The overlap of the dust-proof net should be regular, and there should be no chaotic overlap. The left and right overlaps are less than 30 mm, and the upper and lower overlaps should not exceed 5 mm. For sheets exceeding 4.5 meters, spacers should be added at 2.25 meters. Sheets for special spacers, 8mm bolts. Before tapping the self-tapping, the aluminum strip should be punched first. The self-tapping should be horizontal and vertical, and a cap should be completed immediately. Check the contamination of the dust filter and deal with it immediately. Use an angle grinder to cut off the excess part of the dust net at the steel arch, and use white paint for repainting on the cut section;
(6)顶部防尘网沿扁铁方向隔50mm打螺丝,钢拱架处上下两排扁铁上都要打自攻丝固定,确保间隔50mm都有自攻丝紧固。(6) Screw the top dust-proof net at intervals of 50mm along the direction of the flat iron. The upper and lower rows of the flat iron at the steel arch should be fixed with self-tapping screws to ensure that there are self-tapping screws at intervals of 50mm.
13、桁架托梁侧面也可以安装微孔防尘网。安装方法同上。13. The side of the truss joist can also be installed with a microporous dust filter. The installation method is the same as above.
以上显示和描述了本实用新型的基本原理和主要特征和本实用新型的优点,并且本实用新型使用到的标准零件均可以从市场上购买,异形件根据说明书的和附图的记载均可以进行订制,各个零件的具体连接方式均采用现有技术中成熟的螺栓铆钉、焊接等常规手段,机械、零件和设备均采用现有技术中,常规的型号,膜材和阳光板、加上控制电路连接采用现有技术中常规的连接方式,在此不再详述。The basic principle and main features of the present invention and the advantages of the present invention are shown and described above, and the standard parts used in the present invention can be purchased from the market, and the special-shaped parts can be made according to the description in the description and the drawings. Customized, the specific connection method of each part adopts the conventional methods such as mature bolts, rivets and welding in the existing technology, and the machinery, parts and equipment adopt the existing technology, conventional models, membrane materials and solar panels, plus control The circuit connection adopts the conventional connection method in the prior art, which will not be described in detail here.
上面结合附图对本实用新型的实施例作了详细说明,但是本实用新型并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本实用新型宗旨的前提下作出各种变化。The embodiments of the present utility model have been described in detail above in conjunction with the accompanying drawings, but the present utility model is not limited to the above-mentioned embodiments, and within the scope of knowledge possessed by those of ordinary skill in the art, it is also possible to do so without departing from the purpose of the present utility model. make various changes.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921789466.9U CN211691716U (en) | 2019-10-23 | 2019-10-23 | Large-span closed stockyard structure for multiple stackers and reclaimers |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921789466.9U CN211691716U (en) | 2019-10-23 | 2019-10-23 | Large-span closed stockyard structure for multiple stackers and reclaimers |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211691716U true CN211691716U (en) | 2020-10-16 |
Family
ID=72785547
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201921789466.9U Expired - Fee Related CN211691716U (en) | 2019-10-23 | 2019-10-23 | Large-span closed stockyard structure for multiple stackers and reclaimers |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211691716U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110905261A (en) * | 2019-10-23 | 2020-03-24 | 山西联邦环境工程有限公司 | Ultra-large-span closed stock ground structure for multiple material piling and taking machines and construction method thereof |
| CN112323977A (en) * | 2020-11-18 | 2021-02-05 | 山西联邦环境工程有限公司 | A prefabricated large-span cold-formed solid web arch structure |
-
2019
- 2019-10-23 CN CN201921789466.9U patent/CN211691716U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110905261A (en) * | 2019-10-23 | 2020-03-24 | 山西联邦环境工程有限公司 | Ultra-large-span closed stock ground structure for multiple material piling and taking machines and construction method thereof |
| CN110905261B (en) * | 2019-10-23 | 2025-06-24 | 科顿科学(山西)股份有限公司 | Ultra-large span closed material yard structure for multiple stackers and reclaimers and construction method thereof |
| CN112323977A (en) * | 2020-11-18 | 2021-02-05 | 山西联邦环境工程有限公司 | A prefabricated large-span cold-formed solid web arch structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105019639B (en) | Overhead cantilever formwork and its construction method | |
| CN103635643B (en) | Construction Method of Reinforced Concrete Cylinder in High-rise Steel Structure Building | |
| CN208072213U (en) | A kind of steel box-girder installation temporary support | |
| CN106760529B (en) | Roof steel truss sliding assembly construction platform and installation method | |
| CN104929373B (en) | Large span Square Steel Tubes Truss and its accumulation slippage construction method | |
| CN202227476U (en) | High-altitude large-span overhung corridor-type reinforced concrete structure | |
| CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
| CN105569358A (en) | Construction method of special-shaped curved surface roof with large span and multiple curvatures | |
| CN103291076A (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
| CN110847062A (en) | Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory | |
| CN101871259B (en) | Construction method of integral sliding scaffold for steel grid construction | |
| CN101775896B (en) | Rigid hanging scaffolding for installation of steel roof equipment piping | |
| CN109989348A (en) | Cantilever formwork for concrete construction and construction method thereof | |
| CN114214920A (en) | Large-span double-layer combined construction steel truss arch bridge and construction method thereof | |
| CN212562469U (en) | A new formwork support system for unit truss concrete frame structure | |
| CN110905261B (en) | Ultra-large span closed material yard structure for multiple stackers and reclaimers and construction method thereof | |
| CN112575948A (en) | Truss string beam and cantilever truss combined roof truss and construction method | |
| CN211691716U (en) | Large-span closed stockyard structure for multiple stackers and reclaimers | |
| CN111155759A (en) | A new type unit truss type concrete frame structure formwork support system and its construction method | |
| CN104775606A (en) | Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof | |
| CN115288449A (en) | Construction method of middle support installation of large-span grid frame | |
| CN102635061A (en) | Mountain stream river-crossing inclined zipper trestle and hoisting method thereof | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| CN212201400U (en) | Assembled steel structure external hanging type protective frame | |
| CN214531431U (en) | Truss combination roof truss of opening string roof beam and encorbelmenting |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address |
Address after: 030045 No. 2, umbrella tree Jinxiuyuan, No. 2, Jingyuan Road, Yangqu Industrial Park, Shanxi transformation and comprehensive reform demonstration zone, Taiyuan City, Shanxi Province Patentee after: Coton Environmental Science Co.,Ltd. Address before: 030045 No. 2, san'er Shu Jin Xiu Yuan, No. 2, Jingyuan Road, Xinghualing District, Taiyuan City, Shanxi Province Patentee before: SHANXI LIANBANG ENVIRONMENT ENGINEERING Co.,Ltd. |
|
| CP03 | Change of name, title or address | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201016 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
