CN116043713A - A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air - Google Patents

A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air Download PDF

Info

Publication number
CN116043713A
CN116043713A CN202310126561.5A CN202310126561A CN116043713A CN 116043713 A CN116043713 A CN 116043713A CN 202310126561 A CN202310126561 A CN 202310126561A CN 116043713 A CN116043713 A CN 116043713A
Authority
CN
China
Prior art keywords
lifting
steel
section
cranes
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310126561.5A
Other languages
Chinese (zh)
Inventor
卢冠楠
刘丹娜
邵文泽
王钢
田伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202310126561.5A priority Critical patent/CN116043713A/en
Publication of CN116043713A publication Critical patent/CN116043713A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种悬索桥钢梁竖拼竖提空中转体架设方法,包括以下步骤:在索塔边跨侧两主索上采用临时索夹悬吊一起吊平台,起吊平台上安装4台提升吊机;将第一个钢梁节段运至塔下并竖向放置,用两台吊机提升第一个梁段;将第二个梁段运至第一个梁段下方与第一个梁段焊接,并用同样方法将多个节段焊接成大节段;竖向提升大节段钢梁,4台吊机配合将钢梁空中转体至水平状态,然后安装大节段钢梁;移动临时索夹架悬空起吊平台至下一位置,用同样方法依次安装后续钢梁。本发明不需要搭设支架,施工成本低,速度快,安全性高。

Figure 202310126561

The invention relates to a method for erecting steel girders of a suspension bridge by vertical assembly and vertical lifting in the air, comprising the following steps: using temporary cable clips to suspend a lifting platform on two main cables at the side spans of the cable tower, and installing four lifting cranes on the lifting platform machine; transport the first steel beam section under the tower and place it vertically, use two cranes to lift the first beam section; transport the second beam section below the first beam section and weld it with the first beam section, And use the same method to weld multiple sections into a large section; vertically lift the large section steel beam, and cooperate with 4 cranes to rotate the steel beam to a horizontal state in the air, and then install the large section steel beam; move the temporary cable clamp Lift the platform in the air to the next position, and use the same method to install the subsequent steel beams in sequence. The invention does not need to set up supports, and has low construction cost, high speed and high safety.

Figure 202310126561

Description

一种悬索桥钢梁竖拼竖提空中转体架设方法A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air

技术领域technical field

本发明属于桥梁施工技术领域,涉及一种大跨度钢结构悬索桥施工,具体涉及一种悬索桥钢梁安装施工方法。The invention belongs to the technical field of bridge construction, and relates to the construction of a long-span steel structure suspension bridge, in particular to a method for installing and constructing a suspension bridge steel girder.

背景技术Background technique

大跨度悬索桥钢梁通常采用缆索吊进行吊装。钢梁分节段加工,运至缆索吊的吊点下方,缆索吊起吊梁段、携梁行走到安装位置,安装吊索,并与已安装梁段焊接。Steel girders of long-span suspension bridges are usually hoisted by cable cranes. Steel girders are processed in sections, transported to the bottom of the lifting point of the cable crane, the cable lifts the lifting beam section, carries the beam to the installation position, installs the sling, and welds with the installed beam section.

缆索吊安装方法应用较广且技术成熟,但只局限于悬索桥主跨钢梁安装,无法适用于无索区和边跨梁段的吊装。The cable crane installation method is widely used and the technology is mature, but it is only limited to the installation of steel girders in the main span of suspension bridges, and cannot be applied to the hoisting of cable-free areas and side span girder sections.

悬索桥无索区是指悬索桥主塔下方的部分梁段,由于受塔身影响,无法安装吊索,该部分梁段需要支撑在主塔的下横梁上,或边设有桥墩,边跨梁段支撑在桥墩上,不设吊索,因此称为无索区。由于塔身阻挡,缆索吊无法直接将梁段起吊到无索区安装位置上方;对于边跨梁段,由于缆索吊的缆索在此区域垂度较大,缆索吊也无法直接吊装边跨钢梁梁段。The cable-free area of the suspension bridge refers to the part of the beam section under the main tower of the suspension bridge. Due to the influence of the tower body, the sling cannot be installed. It is supported on the pier without slings, so it is called the no-cable area. Due to the blockage of the tower, the cable crane cannot directly lift the beam section above the installation position of the cable-free area; for the side-span beam section, the cable crane cannot directly lift the side-span steel beam because the cable of the cable crane has a large sag in this area Beam section.

目前对悬索桥无索区和边跨梁段安装,常采用的方法有缆载吊机法、支架法、顶推法、滑移法,或上述方法组合使用。At present, for the installation of the cable-free area and the side-span beam section of the suspension bridge, the commonly used methods include the cable-mounted crane method, the bracket method, the jacking method, the sliding method, or a combination of the above methods.

由于缆载吊机直接行走在悬索桥的主索上,采用缆载吊机安装无索区梁段时,也无法直接将梁段起吊到安装位置,缆载吊机起吊梁段行走到靠近无索区后,采用荡移法将梁段荡移到下横梁和支架上;采用缆载吊机安装边跨梁段时,由于边跨主索高度较低,一般无法带梁行走,需要与支架法结合使用。中国专利CN2793147Y公开了一种多跨悬索桥无索区钢梁吊装方法,采用的就是缆载吊机与支架结合的方法,其包括一活动支架和一固定支架,先由缆载吊机将钢梁起吊到活动支架上,再由活动支架将钢梁移动到安装位置进行安装,或缆载吊机再空载移动到安装位置对钢梁进行吊装。Since the cable-loaded crane directly walks on the main cables of the suspension bridge, when the cable-loaded crane is used to install the beam section in the cable-free area, it cannot directly lift the beam section to the installation position. After the area, use the swing method to move the beam section to the lower beam and the support; when using the cable-loaded crane to install the side span beam section, due to the low height of the main cable of the side span, it is generally impossible to walk with the beam, so it needs to be used in combination with the support method . Chinese patent CN2793147Y discloses a method for hoisting steel girders in the cable-free area of a multi-span suspension bridge, which uses a method of combining a cable-loaded crane with a bracket, which includes a movable bracket and a fixed bracket, and the steel beam is first lifted by the cable-loaded crane Lift it to the movable support, and then move the steel beam to the installation position for installation by the movable support, or move the cable-loaded crane to the installation position without load to hoist the steel beam.

其余的安装方法,包括支架法、顶推法、滑移法等,也都需要搭设支架。The rest of the installation methods, including bracket method, jacking method, sliding method, etc., also need to set up brackets.

大跨悬索桥往往通航净空比较高,钢梁距离地面的高差较大,山区悬索桥由于地形条件决定,边跨塔根部钢梁距离地面的高度往往也较大,因此搭设支架存在材料投入大、作业安全风险高、施工周期长的问题;尤其对于缆载吊机法,还存在设备租赁、钢梁场内运输滑道及便道、基础处理等费用,安装、拆除、进退场等工序,成本更高。Long-span suspension bridges often have relatively high navigation clearance, and the height difference between the steel girder and the ground is relatively large. Due to the topographical conditions of the suspension bridge in mountainous areas, the height of the steel girder at the root of the side-span tower from the ground is often relatively large, so there is a large investment in materials and labor in erecting the bracket. The problems of high safety risks and long construction period; especially for the cable-loaded crane method, there are still equipment rental, transportation slides and sidewalks in the steel beam field, foundation treatment and other costs, installation, dismantling, entry and exit and other procedures, the cost is higher .

发明内容Contents of the invention

本发明的目的是提供一种悬索桥钢梁竖拼竖提空中转体架设方法,解决现有的悬索桥无索区和边跨梁段安装施工方法普遍存在费用高、风险大、效率低等问题。The purpose of the present invention is to provide a method for erecting steel girders of suspension bridges with vertical splicing and lifting in the air, so as to solve the problems of high cost, high risk, and low efficiency generally existing in the installation and construction methods of cable-free areas and side-span girder sections of suspension bridges.

本发明的技术方案如下:Technical scheme of the present invention is as follows:

一种悬索桥钢梁竖拼竖提空中转体架设方法,其特征在于,包括以下步骤:A method for erecting steel girders of a suspension bridge vertically assembled and vertically lifted in the air, characterized in that it comprises the following steps:

(1)安装悬空起吊平台:在悬索桥索塔边跨侧两主索上靠近索塔位置分别安装两个临时索夹,每根主索上的两临时索夹有一定间距,4个临时索夹通过钢丝绳悬吊一起吊平台,所述起吊平台上安装4台提升吊机,其中两台吊机朝向索塔,另两台朝向岸边,每台吊机连接一吊绳;(1) Install the suspended lifting platform: Install two temporary cable clips on the two main cables on the side span of the suspension bridge cable tower near the cable tower. There is a certain distance between the two temporary cable clips on each main cable, and 4 temporary cable clips. A hoisting platform is suspended by wire ropes, and 4 hoisting cranes are installed on the hoisting platform, two of which are facing the cable tower, and the other two are facing the shore, and each crane is connected with a sling;

(2)提升第一个梁段:将第一个钢梁节段运至塔根边跨一侧并竖向放置,在第一个梁段顶部焊接两个吊耳,靠近索塔的两台吊机下放吊绳与第一个梁段的吊耳连接,将第一个梁段提升大于一个梁段的高度;(2) Lifting the first beam section: transport the first steel beam section to the side span of the tower root and place it vertically, weld two lifting lugs on the top of the first beam section, and the two sets close to the cable tower The lifting rope of the crane is lowered to connect with the lug of the first beam section, and the first beam section is lifted higher than the height of one beam section;

(3)竖向拼接梁段:将第二个梁段运至第一个梁段下方并竖向放置,将第一个梁段下方到第二个梁段上,将两个梁段焊接;两台吊机将焊接后的梁段提升大于一个梁段的高度,采用同样的方法焊接后续梁段,将两个或多个节段焊接成一个大节段钢梁;在最下一个梁段朝向岸边侧焊接两个吊耳;(3) Vertically splicing beam sections: transport the second beam section below the first beam section and place it vertically, place the first beam section below the second beam section, and weld the two beam sections; The crane lifts the welded beam section higher than the height of one beam section, and uses the same method to weld subsequent beam sections to weld two or more sections into a large section steel beam; when the last beam section faces the shore Two lifting lugs are welded on the side;

(4)钢梁起吊:两台吊机将焊接完成的大节段钢梁整体提升到超过悬索桥下横梁的高度;(4) Steel girder lifting: Two cranes lift the welded large segment steel girder to the height of the lower beam of the suspension bridge;

(5)钢梁空中转体:起吊平台上朝向岸边的两个吊机通过吊绳连接钢梁最下节段上的吊耳并收紧吊绳向上提升,同时朝向主塔的两台吊机缓慢放松吊绳,将钢梁空中转体至水平状态;(5) Steel girder swivel in the air: the two cranes facing the shore on the lifting platform connect the lifting lugs on the lowermost section of the steel beam through the lifting rope and tighten the lifting rope to lift upwards. At the same time, the two cranes facing the main tower The machine slowly loosens the sling, and rotates the steel beam in the air to a horizontal state;

(6)安装钢梁:4台吊机同步下放钢梁至安装高度,在边跨设有桥墩的情况下,将钢梁支撑在桥墩上;在边跨设计有吊索的情况下,将钢梁与吊索连接;然后吊机缓慢放松吊绳,直至载荷为零,完成一跨或一个大节段的钢梁安装;(6) Installation of steel girders: four cranes lower the steel girders to the installation height synchronously. The beam is connected with the sling; then the crane slowly releases the sling until the load is zero, completing the installation of a span or a large section of steel girder;

(7)将临时索夹、悬空起吊平台移动到下一钢梁安装位置,按照上述方法安装后续钢梁。(7) Move the temporary cable clamp and the suspended lifting platform to the installation position of the next steel beam, and install the subsequent steel beam according to the above method.

本发明是一种全新的悬索桥钢梁安装方法,可以安全快捷进行无索区及边跨钢梁的安装,与现有技术相比,至少具有以下优点:The present invention is a brand-new installation method of steel girders of suspension bridges, which can safely and quickly install cable-free areas and side-span steel girders. Compared with the prior art, it has at least the following advantages:

与传统上的支架法、顶推法、滑移法相比,本发明节约了场地硬化面积、支架材料的投入和支架搭设、拆除的人工及机械费用,并降低了安全作业风险;Compared with the traditional support method, push method, and sliding method, the present invention saves the hardening area of the site, the input of support materials, and the labor and mechanical costs of support erection and removal, and reduces the risk of safe operation;

与缆载吊机方法相比,由于无索区和边跨钢梁数量少,采用缆载吊机所需的租金、加工改制费用、滑道及基础处理费相对较高,采用本发明的费用大大低于缆载吊机法,而且本发明还可以降低缆载吊机组拼、拆除的高空作业风险,节约工期。Compared with the cable-loaded crane method, due to the small number of cable-free areas and side-span steel beams, the rent, processing and restructuring costs, slideways and foundation treatment fees required for the cable-loaded crane are relatively high. It is much lower than the cable-loaded crane method, and the present invention can also reduce the high-altitude operation risk of assembly and dismantling of the cable-loaded crane unit, and save the construction period.

本发明由于不需要搭设支架,钢梁净空越高,本发明的安装成本优势越突出。Since the present invention does not need to set up supports, the higher the clearance of the steel beam, the more prominent the advantage of the present invention is the installation cost.

附图说明Description of drawings

图1是本发明的施工流程图;Fig. 1 is a construction flowchart of the present invention;

图2是起吊系统的安装状态示意图;Fig. 2 is a schematic diagram of the installation state of the lifting system;

图3是起吊系统将第一个钢梁段竖向起吊到一定高度时的状态示意图;Fig. 3 is a schematic diagram of the state when the hoisting system lifts the first steel beam section vertically to a certain height;

图4是梁段间的竖向拼接状态示意图;Fig. 4 is a schematic diagram of the vertical splicing state between beam sections;

图5是将拼接完成的大节段钢梁竖向起吊的状态示意图;Fig. 5 is a schematic diagram of the state of vertically hoisting the spliced large-segment steel beam;

图6是钢梁在空中转体的状态示意图;Fig. 6 is a schematic diagram of the state of the steel beam rotating in the air;

图7是一个大节段钢梁安装完成后的状态示意图。Fig. 7 is a schematic diagram of the state after the installation of a large section steel beam is completed.

具体实施方式Detailed ways

本发明的施工流程如图1所示,具体施工方法如下:Construction process of the present invention is as shown in Figure 1, and concrete construction method is as follows:

(1)安装悬空起吊平台:如图2所示,在悬索桥索塔1边跨侧两主索2上靠近索塔位置分别安装两个临时索夹3,每根主索2上的两临时索夹3有一定间距,4个临时索夹3通过钢丝绳4悬吊一起吊平台5,所述起吊平台5上安装4台提升吊机6,其中两台吊机朝向索塔,另两台朝向岸边,每台吊机6连接一吊绳7;(1) Install the suspended lifting platform: As shown in Figure 2, two temporary cable clips 3 are respectively installed on the two main cables 2 on the side span side of the suspension bridge cable tower 1 near the cable tower, and the two temporary cable clips on each main cable 2 The clips 3 have a certain distance, and the four temporary cable clips 3 are suspended by the steel wire rope 4 together to lift the platform 5, and four hoisting cranes 6 are installed on the lifting platform 5, two of which are facing the cable tower, and the other two are facing the shore. side, each hoist 6 is connected with a suspension rope 7;

具体实施时,为减轻悬空起吊平台的自重,所述悬空起吊平台5可采用多个钢桁架组拼而成,钢桁架上铺设平台面板。During specific implementation, in order to reduce the self-weight of the suspended hoisting platform, the suspended hoisting platform 5 can be assembled by a plurality of steel trusses, and platform panels are laid on the steel trusses.

(2)提升第一个梁段:如图3所示,将第一个钢梁节段81运至塔根边跨一侧并竖向放置,在第一个梁段顶部焊接两个吊耳,靠近索塔的两台吊机下放吊绳7与第一个梁段81的吊耳连接,将第一个梁段81提升大于一个梁段的高度。(2) Lifting the first beam section: as shown in Figure 3, transport the first steel beam section 81 to the side of the side span of the tower root and place it vertically, and weld two lifting lugs on the top of the first beam section , two cranes near the cable tower lower the suspension rope 7 to connect with the lugs of the first beam section 81, and the first beam section 81 is promoted to be greater than the height of a beam section.

(3)竖向拼接梁段:如图4所示,将第二个梁段82运至第一个梁段81下方并竖向放置,将第一个梁段下方到第二个梁段上,将两个梁段焊接;两台吊机将焊接后的梁段提升大于一个梁段的高度,采用同样的方法焊接后续梁段,将两个或多个节段焊接成一个大节段钢梁8;在最下一个梁段朝向岸边侧焊接两个吊耳。(3) Vertical splicing of beam sections: as shown in Figure 4, the second beam section 82 is transported to the bottom of the first beam section 81 and placed vertically, and the bottom of the first beam section is placed on the second beam section , weld the two beam sections; two cranes lift the welded beam section to a height greater than one beam section, and use the same method to weld subsequent beam sections to weld two or more sections into a large steel section Beam 8; Weld two lifting lugs on the side of the bottom beam section facing the shore.

(4)钢梁起吊:如图5所示,两台吊机将焊接完成的大节段钢梁8整体提升到超过悬索桥下横梁的高度。(4) Steel girder hoisting: as shown in Figure 5, two cranes lift the welded large section steel girder 8 as a whole to a height exceeding the lower beam of the suspension bridge.

(5)钢梁空中转体:如图6所示,起吊平台上朝向岸边的两个吊机通过吊绳7连接钢梁8最下节段上的吊耳并收紧吊绳向上提升,同时朝向主塔的两台吊机缓慢放松吊绳,将钢梁8空中转体至水平状态。(5) steel beam aerial rotation: as shown in Figure 6, the two cranes facing the shore on the lifting platform connect the lifting lugs on the lowermost section of the steel beam 8 through the lifting rope 7 and tighten the lifting rope to lift upwards. At the same time, the two cranes towards the main tower slowly loosen the suspension ropes, and the steel beam 8 is swiveled in the air to a horizontal state.

(6)安装钢梁:如图7所示,4台吊机同步下放钢梁至安装高度;对于塔下无索区钢梁,可将钢梁荡移到索塔下横梁上并安装固定;对于边跨钢梁,在边跨设有桥墩9的情况下,将钢梁8支撑在桥墩9上;在钢梁与主缆间设计有吊索的情况下,将钢梁与吊索连接;然后吊机缓慢放松吊绳,直至吊绳载荷为零,完成一跨或一个大节段的钢梁安装。(6) Installation of steel beams: as shown in Figure 7, four cranes lowered the steel beams to the installation height synchronously; To span steel girders, when the side span is provided with pier 9, support the steel girder 8 on the pier 9; if there is a sling between the steel girder and the main cable, connect the steel girder to the sling; then hang The machine slowly loosens the suspension rope until the load of the suspension rope is zero, and completes the steel beam installation of a span or a large section.

(7)将临时索夹、悬空起吊平台移动到下一钢梁安装位置,按照上述方法安装后续钢梁。(7) Move the temporary cable clamp and the suspended lifting platform to the installation position of the next steel beam, and install the subsequent steel beam according to the above method.

Claims (2)

1. The overhead swivel erection method for the vertical splicing and vertical lifting of the suspension bridge steel beam is characterized by comprising the following steps of:
(1) Installing a suspended hoisting platform: two temporary rope clamps are respectively arranged at positions, close to the rope towers, on two main ropes at the side of the side span of the rope towers of the suspension bridge, a certain distance is reserved between the two temporary rope clamps on each main rope, 4 temporary rope clamps suspend a lifting platform together through a steel wire rope, 4 lifting cranes are arranged on the lifting platform, two cranes face the rope towers, the other two cranes face the shore, and each crane is connected with a lifting rope;
(2) Lifting the first beam section: the first girder segment is transported to one side of the tower root side span and vertically placed, two lifting lugs are welded on the first girder Duan Dingbu, and two cranes close to the cable tower are connected with the lifting lugs of the first girder segment by lowering lifting ropes, so that the first girder segment is lifted to be greater than the height of one girder segment;
(3) Vertical spliced girder section: placing a second beam Duan Yun to a first beam Duan Xiafang vertically, placing a first beam section below to a second beam section, and welding the two beam sections; the two cranes lift the welded beam sections to a height greater than that of one beam section, and the subsequent beam sections are welded by adopting the same method, so that two or more sections are welded into a large-section steel beam; welding two lifting lugs on the lowest beam section towards the bank side;
(4) And (3) hoisting a steel beam: the two cranes integrally lift the welded large-section steel girder to a height exceeding the height of the lower cross beam of the suspension bridge;
(5) Overhead steel beam swivel: two cranes facing the shore on the hoisting platform are connected with lifting lugs on the lowest section of the steel beam through lifting ropes and tighten the lifting ropes to lift upwards, and meanwhile, the two cranes facing the main tower slowly loosen the lifting ropes to turn the steel beam into a horizontal state in the air;
(6) And (3) installing a steel beam: synchronously lowering the steel beams to the installation height by 4 cranes, and supporting the steel beams on the piers under the condition that the piers are arranged on the side spans; under the condition that a sling is designed on the side span, connecting the steel beam with the sling; then the crane slowly loosens the lifting rope until the load is zero, and the installation of one span or one large-section steel beam is completed;
(7) And moving the temporary cable clamp and the suspended hoisting platform to the next steel beam installation position, and installing the subsequent steel beams according to the method.
2. The method for erecting the suspension bridge steel girder vertical splicing vertical lifting overhead swivel according to claim 1, wherein the method comprises the following steps: the suspended lifting platform is formed by assembling a plurality of trusses, and platform panels are paved on the steel trusses.
CN202310126561.5A 2023-02-05 2023-02-05 A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air Pending CN116043713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310126561.5A CN116043713A (en) 2023-02-05 2023-02-05 A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310126561.5A CN116043713A (en) 2023-02-05 2023-02-05 A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air

Publications (1)

Publication Number Publication Date
CN116043713A true CN116043713A (en) 2023-05-02

Family

ID=86127709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310126561.5A Pending CN116043713A (en) 2023-02-05 2023-02-05 A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air

Country Status (1)

Country Link
CN (1) CN116043713A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117051709A (en) * 2023-08-10 2023-11-14 中交路桥建设有限公司 Swing-moving vertical lifting installation method for side-span beam sections
CN117071437A (en) * 2023-08-05 2023-11-17 中铁广州工程局集团桥梁工程有限公司 A method for erecting continuous rigid frame side-span steel beams
CN117144802A (en) * 2023-08-10 2023-12-01 中交路桥建设有限公司 Swing installation method of side span beam sections
CN119083306A (en) * 2024-08-15 2024-12-06 中交路桥华南工程有限公司 Swing-shift vertical assembly construction method for side span beam segments

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08311819A (en) * 1995-05-18 1996-11-26 Tomoe Corp Rotating construction method for bridges with high piers
CN208328711U (en) * 2018-05-28 2019-01-04 山东省路桥集团有限公司 The pivotal erection crane of steel box girder assembling
CN109440660A (en) * 2018-12-10 2019-03-08 中交四公局第五工程有限公司 Suspension bridge wide cut concrete stiffening girder cable crane turns installation structures and methods
CN109653094A (en) * 2018-11-28 2019-04-19 中国铁建大桥工程局集团有限公司 A kind of suspension bridge main span is without hoist cable beam section installation method
CN110409322A (en) * 2019-08-27 2019-11-05 中铁二局集团有限公司 A kind of bridge steel upright post hoisting rotary body device and swivel method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08311819A (en) * 1995-05-18 1996-11-26 Tomoe Corp Rotating construction method for bridges with high piers
CN208328711U (en) * 2018-05-28 2019-01-04 山东省路桥集团有限公司 The pivotal erection crane of steel box girder assembling
CN109653094A (en) * 2018-11-28 2019-04-19 中国铁建大桥工程局集团有限公司 A kind of suspension bridge main span is without hoist cable beam section installation method
CN109440660A (en) * 2018-12-10 2019-03-08 中交四公局第五工程有限公司 Suspension bridge wide cut concrete stiffening girder cable crane turns installation structures and methods
CN110409322A (en) * 2019-08-27 2019-11-05 中铁二局集团有限公司 A kind of bridge steel upright post hoisting rotary body device and swivel method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117071437A (en) * 2023-08-05 2023-11-17 中铁广州工程局集团桥梁工程有限公司 A method for erecting continuous rigid frame side-span steel beams
CN117071437B (en) * 2023-08-05 2025-06-10 中铁广州工程局集团桥梁工程有限公司 A method for erecting continuous rigid frame side span steel beams
CN117051709A (en) * 2023-08-10 2023-11-14 中交路桥建设有限公司 Swing-moving vertical lifting installation method for side-span beam sections
CN117144802A (en) * 2023-08-10 2023-12-01 中交路桥建设有限公司 Swing installation method of side span beam sections
CN117051709B (en) * 2023-08-10 2025-11-28 中交路桥建设有限公司 Swinging type vertical lifting installation method for side span beam section
CN119083306A (en) * 2024-08-15 2024-12-06 中交路桥华南工程有限公司 Swing-shift vertical assembly construction method for side span beam segments

Similar Documents

Publication Publication Date Title
CN116043713A (en) A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air
CN104674668B (en) A kind of method by cable-hoisting construction girder section
CN103911956B (en) A kind of large span stayed-cable bridge steel truss girder mounting method
CN111335187B (en) Construction process for triangular area of open-web rigid frame bridge
CN115506604B (en) Method for installing first truss of large-span steel structure
CN114182647B (en) Construction method for lifting and turning weak arch
JP7324626B2 (en) Lifted load moving device, removal method of existing bridge, and installation method of bridge members
CN105803947A (en) Integral traversing system and method for portal-type full space support of cast-in-situ box girder
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN106744351A (en) The method of hoisting the main girder of the cable-stayed bridge by using the cable crane
CN111519545A (en) Pier and capping beam integrated construction platform and construction method thereof
CN110468743B (en) A mobile hanger and construction method for the renovation of old bridge pier caps
CN110159057A (en) Technological transformation workshop chimney construction method of installation
CN116853963B (en) A hoisting device and hoisting method for main beam of cable-stayed bridge
CN110316662B (en) Installation and construction method of large-span portal crane
CN102926329A (en) Device dedicated for lifting steel box beam of small and medium-sized long-span suspension bridge and lifting method
CN107419907A (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN116084302A (en) A Construction Method for Construction of Concrete Box Girder Sections of Cable-Stayed Bridges Using Pull Cables and Hanging Baskets
CN114277688B (en) Erecting machine
WO2024148716A1 (en) Method for erecting curved steel truss cable-stayed bridge
CN117051709A (en) Swing-moving vertical lifting installation method for side-span beam sections
CN112853993B (en) Large-span suspension bridge assembling construction method
CN116122579A (en) Hoisting method for bidirectional bending dome bracket
CN108612317A (en) A kind of band waves column type gate-type combination steel frame construction installation method
CN206917297U (en) A kind of large-span steel girder upper air installing system in place

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Lu Guannan

Inventor after: Liu Danna

Inventor after: Shao Wenze

Inventor after: Wang Gang

Inventor after: Tian Wei

Inventor after: Yang Ke

Inventor before: Lu Guannan

Inventor before: Liu Danna

Inventor before: Shao Wenze

Inventor before: Wang Gang

Inventor before: Tian Wei