CN103470057A - Method of hoisting high altitude components - Google Patents
Method of hoisting high altitude components Download PDFInfo
- Publication number
- CN103470057A CN103470057A CN201310370998XA CN201310370998A CN103470057A CN 103470057 A CN103470057 A CN 103470057A CN 201310370998X A CN201310370998X A CN 201310370998XA CN 201310370998 A CN201310370998 A CN 201310370998A CN 103470057 A CN103470057 A CN 103470057A
- Authority
- CN
- China
- Prior art keywords
- hoisting
- gan
- lifted
- component
- hands
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 claims description 17
- 238000009434 installation Methods 0.000 claims description 7
- 239000000725 suspension Substances 0.000 claims description 3
- 230000002459 sustained effect Effects 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 3
- 229910000831 Steel Inorganic materials 0.000 abstract description 6
- 239000010959 steel Substances 0.000 abstract description 6
- 230000007306 turnover Effects 0.000 abstract description 2
- 230000000717 retained effect Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The invention discloses a method of hoisting high altitude components. The method includes the steps of a, fixedly connecting a triangular steel frame having a hoisting beam to a steel frame of a moving carriage, mounting a chain block on the hoisting beam, fixing a component to be hoisted with a chain block cable, and hoisting and mounting the component in place through motion of the triangular steel frame and the chain block to form a boom crane. The method is simple and practical; the original vertical transport equipment need not be retained; operational safety is improved for constructors; labor intensity is partly reduced for workers; efficiency of hoisting components is improved effectively, and turnover times of hoisting equipment can be increased.
Description
Technical field
The present invention relates to a kind of novel high-altitude member hoisting construction method, more specifically saying a kind of is applied in high building project in the time of can't utilizing vertical equipment to carry out the lifting component installation, a kind of suggestion in feasible lifting component engineering adopted, facilitate the job practices of member lifting and installation in place.
Background technology
Along with the development highrise building of Modern Construction Technology is more and more, high-altitude lifting component working design is more and more, the Construction of Steel Structure superiority is also more and more important, because constructing, the working vertical transport equipment of general original structure is removed as tower crane, in the aerial installation of height, how to make the constructing operation of steel member safer, convenient, and efficiency is higher, becomes an important content of lighting roof construction.
Existing construction technology: need to utilize vertical transport equipment in original structure construction as tower crane, if having removed construction in later period generally can't carry out, because the lighting roof construction works is not generally too large, guarantee that if the construction of lighting roof steel structure retains former vertical transport equipment will increase a large amount of construction costs.
Summary of the invention
The present invention is for avoiding the existing weak point of above-mentioned prior art, a kind of novel high-altitude member hoisting construction method is provided, so that the lifting component operation in the situation of high-altitude, improve processing safety, reduce labour intensity, the effectively operating efficiency of raising lifting, and lifting appliance is reusable edible all.
Technical solution problem of the present invention adopts following technical scheme:
A kind of high-altitude member hoisting construction method includes following steps:
A, employing are fixed and are connected with the steelframe of movable tray with the triangle steelframe of lifting cross beam, bottle gouard moved by hands is installed on lifting cross beam, by the fixing member to be lifted of bottle gouard moved by hands cable wire, movement by the triangle steelframe and bottle gouard moved by hands erection & lift, member in place, forming lifting appliance is that Ba Gan hangs;
B, Ba Gan is hung to move to and want hoisting component one end, then according to the weight of member to be lifted, Ba Gan is lifted up into to capable counterweight adjustment and form and stablize the lifting system;
When c, hoisting component, member to be lifted two ends be individually fixed on the bottle gouard moved by hands cable wire that two different Ba Gan hang and keep suspension centre in sustained height, by manpower movement Ba Gan, hanging hoisting component is transported to infield;
D, member handling, behind appointed place, are at first docked rear welding by hoisting component with installation component or bolt is connected, and the temporary fixed point of member to be lifted stressed can meet member self off the hook when stressed.
Described movable tray is with roller.
Compared with prior art, beneficial effect of the present invention is as follows:
1, the self-control lifting appliance, can have enough to meet the need use, and be convenient to hoisting component lifting and in place;
2, the constructing operation mode of lifting appliance, can can't utilize former vertical transport equipment or existing lifting appliance to use in the air at height, makes simple and easy, with low cost and make its lifting scope become large in order to meet the construction needs by movable wheel is installed.
The present invention is simple and practical, neither needs to retain former vertical transport equipment, improves again the safety of constructor's operation, has reduced to a certain extent labor strength, effectively raises the efficiency of lifting component, and has improved the lifting appliance number of turnover.
The accompanying drawing explanation
Fig. 1 is that Ba Gan hangs scheme of installation.
The specific embodiment
A kind of high-altitude member hoisting construction method includes following steps:
A, employing are fixed and are connected with the steelframe of movable tray 2 with the triangle steelframe 1 of lifting cross beam, movable tray 2 is with roller, bottle gouard moved by hands 4 is installed on lifting cross beam 3, by the fixing member 5 to be lifted of bottle gouard moved by hands 4 cable wires, movement by triangle steelframe 1 and bottle gouard moved by hands 4 erection & lifts, member in place, forming lifting appliance is that Ba Gan hangs;
B, Ba Gan is hung to move to and want hoisting component one end, then according to the weight of member to be lifted, Ba Gan is lifted up into to capable counterweight adjustment and form and stablize the lifting system;
When c, hoisting component, member to be lifted two ends be individually fixed on the bottle gouard moved by hands cable wire that two different Ba Gan hang and keep suspension centre in sustained height, by manpower movement Ba Gan, hanging hoisting component is transported to infield;
D, member handling, behind appointed place, are at first docked rear welding by hoisting component with installation component or bolt is connected, and the temporary fixed point of member to be lifted stressed can meet member self off the hook when stressed.
Claims (2)
1. a high-altitude member hoisting construction method, is characterized in that, includes following steps:
A, employing are fixed and are connected with the steelframe of movable tray with the triangle steelframe of lifting cross beam, bottle gouard moved by hands is installed on lifting cross beam, by the fixing member to be lifted of bottle gouard moved by hands cable wire, movement by the triangle steelframe and bottle gouard moved by hands erection & lift, member in place, forming lifting appliance is that Ba Gan hangs;
B, Ba Gan is hung to move to and want hoisting component one end, then according to the weight of member to be lifted, Ba Gan is lifted up into to capable counterweight adjustment and form and stablize the lifting system;
When c, hoisting component, member to be lifted two ends be individually fixed on the bottle gouard moved by hands cable wire that two different Ba Gan hang and keep suspension centre in sustained height, by manpower movement Ba Gan, hanging hoisting component is transported to infield;
D, member handling, behind appointed place, are at first docked rear welding by hoisting component with installation component or bolt is connected, and the temporary fixed point of member to be lifted stressed can meet member self off the hook when stressed.
2. a kind of high-altitude according to claim 1 member hoisting construction method, it is characterized in that: described movable tray is with roller.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310370998.XA CN103470057B (en) | 2013-08-22 | 2013-08-22 | A kind of high-altitude component hoisting construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310370998.XA CN103470057B (en) | 2013-08-22 | 2013-08-22 | A kind of high-altitude component hoisting construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103470057A true CN103470057A (en) | 2013-12-25 |
| CN103470057B CN103470057B (en) | 2016-03-23 |
Family
ID=49795085
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310370998.XA Active CN103470057B (en) | 2013-08-22 | 2013-08-22 | A kind of high-altitude component hoisting construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103470057B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110790118A (en) * | 2018-08-03 | 2020-02-14 | 淮安市淮宁钢结构有限公司 | High-altitude component hoisting construction method |
| CN113072008A (en) * | 2021-04-21 | 2021-07-06 | 涡阳县新源泡沫夹心板有限公司 | Hoisting device for steel structure installation |
| CN117513764A (en) * | 2024-01-08 | 2024-02-06 | 北京建工集团有限责任公司 | Sliding method with installation position lower than sliding rail |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003074186A (en) * | 2001-09-07 | 2003-03-12 | Soken Sangyo Kk | Device and method for erection of column steel frame |
| CN201506692U (en) * | 2009-08-10 | 2010-06-16 | 中建三局建设工程股份有限公司 | Roofing steel structure simple lifting device and installation structure thereof |
| CN102383613A (en) * | 2011-11-11 | 2012-03-21 | 天津电力工程监理有限公司 | Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device |
| CN202194393U (en) * | 2011-07-16 | 2012-04-18 | 安徽鸿路钢结构(集团)股份有限公司 | Triangular hoisting structure for steel frame pavement |
-
2013
- 2013-08-22 CN CN201310370998.XA patent/CN103470057B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003074186A (en) * | 2001-09-07 | 2003-03-12 | Soken Sangyo Kk | Device and method for erection of column steel frame |
| CN201506692U (en) * | 2009-08-10 | 2010-06-16 | 中建三局建设工程股份有限公司 | Roofing steel structure simple lifting device and installation structure thereof |
| CN202194393U (en) * | 2011-07-16 | 2012-04-18 | 安徽鸿路钢结构(集团)股份有限公司 | Triangular hoisting structure for steel frame pavement |
| CN102383613A (en) * | 2011-11-11 | 2012-03-21 | 天津电力工程监理有限公司 | Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110790118A (en) * | 2018-08-03 | 2020-02-14 | 淮安市淮宁钢结构有限公司 | High-altitude component hoisting construction method |
| CN113072008A (en) * | 2021-04-21 | 2021-07-06 | 涡阳县新源泡沫夹心板有限公司 | Hoisting device for steel structure installation |
| CN117513764A (en) * | 2024-01-08 | 2024-02-06 | 北京建工集团有限责任公司 | Sliding method with installation position lower than sliding rail |
| CN117513764B (en) * | 2024-01-08 | 2024-04-12 | 北京建工集团有限责任公司 | Sliding method with installation position lower than sliding rail |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103470057B (en) | 2016-03-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103708360B (en) | Swing arm tower crane, standard knot introduction system thereof and standard knot introduction method | |
| CN203255914U (en) | Unit-typed curtain wall lifting device | |
| CN202848940U (en) | Chamber roof truss overall declining removal device of large gas chamber | |
| CN103470057A (en) | Method of hoisting high altitude components | |
| CN203128099U (en) | Slipping type pipeline lifting device | |
| CN205114843U (en) | Prefabricated post hoist device with unhook function | |
| CN201634333U (en) | Super-altitude gantry crane | |
| CN103264966A (en) | Self-hoisting device and method of dismounting member of tower crane | |
| CN202731270U (en) | Movable platform for aerial installation operation of space steel structure | |
| CN204752012U (en) | Wall -hanging miniature hoist | |
| CN204751885U (en) | Anchor clamps are changed in hoist and mount of big wheel of overhead traveling crane | |
| CN202729645U (en) | Tower crane with elevator | |
| CN205257816U (en) | Be used for lifting machine in wind generating set cabin | |
| CN204324748U (en) | A kind of large-scale gas storage holder Steel Structure Installation hoisting device | |
| CN103803395A (en) | Hydraulic motor installation hoisting beam as well as application thereof | |
| CN201864517U (en) | Small-size member hoisting tool | |
| CN203284098U (en) | Disassembled and assembled part self-lifting device for tower crane | |
| CN202265781U (en) | Bridge angle cradle with triangular truss | |
| CN204369396U (en) | Steel plate strip hanging apparatus | |
| CN203754332U (en) | Mobile type net frame spare part lifting device | |
| CN105401699A (en) | Light roof panel installation walking vehicle and method for installing roof panels | |
| CN202687853U (en) | High-altitude hoisting device | |
| CN201834702U (en) | Pulley type nacelle hanging mechanism | |
| CN203728417U (en) | Hoisting device of belt conveyor roller | |
| CN102372235A (en) | Pulley type suspension mechanism for hanging basket |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |