title Node.js 24 Upgrade Project
description Upgrade LightSpeed .github from Node.js 22 to Node.js 24 — comprehensive project documentation
created_date 2026-08-29
last_updated 2026-08-29
status active

Node.js 24 Upgrade Project

Status: ✅ Phase 1 Complete — Phase 2 Ready
Timeline: 4–5 hours over 1–2 days
Risk Level: 🟡 Medium
Decision: Phase 1 audit complete; package.json upgraded; proceeding to Phase 2

Project Overview

This project upgrades the LightSpeed .github control plane from Node.js 22 to Node.js 24 — aligning .nvmrc with package.json engines, enabling advanced GitHub API scripts and issue maintenance workflows, and modernising the runtime environment.

Why This Upgrade?

  • Alignment gap — .nvmrc already specifies Node 24, but package.json previously required >=22.0.0 (now fixed)
  • Business requirement — Advanced GitHub API scripts and issue maintenance workflows require Node 24+ features
  • Modern runtime — Node 24 brings V8 improvements, better performance, and modern JavaScript features
  • Consistency — Single source of truth across all workflows and developer environment

Why Node 24, not staying on 22?

  • Explicit need — Your advanced issue maintenance and GitHub API scripts require Node 24 features
  • Future-proof — Node 22 LTS support ends April 30, 2027 (~8 months away)
  • Already configured — .nvmrc already specifies Node 24 (just not documented in package.json)
  • Deliberate choice — This is a forward-looking decision, not a reactive fix

Project Structure

This folder contains comprehensive documentation for planning and executing the upgrade:

.github/projects/active/nodejs-upgrade-2026-q4/
├── README.md                    ← You are here
├── NODEJS_UPGRADE_PLAN.md       ← Complete strategy & phases
├── EXECUTION_PROMPTS.md         ← Ready-to-use prompts per phase
├── QUICK_REFERENCE.md           ← Single-page tracking checklist
├── INVENTORY.md                 ← (Generated during Phase 1)
├── TEST_MATRIX.md               ← (Generated during Phase 1)
├── BREAKING_CHANGES_AUDIT.md    ← (Generated during Phase 1)
└── COMPLETION_REPORT.md         ← (Generated after Phase 5)

Document Quick Links

Document Purpose Audience Read Time
NODEJS_UPGRADE_PLAN.md Complete strategy, 5 phases, risk assessment Planners, decision-makers 20 min
EXECUTION_PROMPTS.md Copy-paste prompts for each phase Agents executing the work 5 min per phase
QUICK_REFERENCE.md One-page checklist for tracking progress Project lead, team 2 min

Current State Analysis

Version Inventory

Aspect Current Target
package.json engines >=22.0.0 >=24.0.0
.nvmrc 24 24 ✓ (no change)
Workflows using Node 22 16 0
Workflows using Node 24 0 (uses .nvmrc) 16 (standardised)
Workflows explicit Node versions 1 (linting.yml) 0 (all use .nvmrc)

Key Mismatch: .nvmrc specifies Node 24, but package.json only requires >=22.0.0


Five-Phase Upgrade Plan

Phase Title Duration Scope Blocker
1 Audit & Documentation 30 min Inventory versions, create test matrix, plan No
2 Local Upgrade 45 min Update package.json, run npm update, commit No
3 Test & Validation 1–1.5 hours Full test suite, validations, breaking change audit Yes
4 Workflow Standardisation 45 min Standardise all workflows to use .nvmrc No
5 CI/CD Verification & Merge 30 min PR, CI checks, merge to develop, complete Yes

Total: ~4–5 hours (can be split over 1–2 days)

Phase Details

See NODEJS_UPGRADE_PLAN.md for:

  • Detailed objectives per phase
  • Step-by-step execution instructions
  • Success criteria
  • Rollback procedures
  • Risk assessment
  • Complete timeline

Key Differences from Node 22 Upgrade

Aspect Node 22 Upgrade Node 24 Upgrade
Starting version 20.x 22.x
Reason EOL timeline, active warnings Business requirement, alignment
.nvmrc status Needs update Already correct ✓
package.json status Needs update Needs alignment
Risk level Low Medium (larger jump: 22 → 24)
Dependency updates ~100 packages ~50–100 packages
Post-merge monitoring 3 days 3 days (same protocol)

Success Criteria

All of the following must be true after execution:

  • ✓ package.json updated to Node >=24.0.0
  • ✓ All tests pass with Node 24 (full test suite)
  • ✓ All validation scripts pass (npm run validate:all)
  • ✓ All workflows standardised (use .nvmrc consistently)
  • ✓ All CI checks pass on the PR
  • ✓ PR merged to develop with squash commit
  • ✓ No Node.js version warnings in workflow output
  • ✓ Post-merge monitoring shows no regressions (3 days)
  • ✓ All advanced GitHub API scripts and issue maintenance workflows operational

Timeline & Effort

Phase Duration Effort Owner
Phase 1: Audit 30 min Low [Agent / Designer]
Phase 2: Local Upgrade 45 min Low [Agent]
Phase 3: Validation 1–1.5 hours Medium [Agent]
Phase 4: Workflows 45 min Medium [Agent]
Phase 5: Merge & Close 30 min Low [Agent]
Total ~4–5 hours Medium [Team]

Can be executed in one session or split over 2 days (e.g., Phase 2–3 on Day 1, Phase 4–5 on Day 2).


Risk Assessment

Risk Probability Impact Mitigation
Breaking changes in dependencies 10% High Phase 3 comprehensive testing; pin if needed
GitHub API script incompatibility 5% Medium Phase 3 validates all scripts; test in Node 24
V8 engine changes affecting performance 5% Low Phase 2–3 performance benchmarking
Workflow runtime compatibility 3% Medium Phase 4 syntax validation and linting
npm version conflicts 2% Low Phase 2 validates compatibility
Rollback needed 2% Low All commits atomic; easy revert

Overall Risk Level: 🟡 MEDIUM

Higher than Node 22 upgrade (Low) due to larger version jump (2 major versions: 22 → 24) and dependency volatility. Mitigated by Phase 3 comprehensive testing and Phase 4 workflow validation.


Rollback Plan

If any phase fails, rollback is simple:

  1. Phases 1–2: No merged commits yet; discard branch
  2. Phase 3: If tests fail, identify breaking dependency, pin it (e.g., package@specific-version), re-run tests
  3. Phase 4: Discard workflow changes, re-do with fixes
  4. Phase 5: If CI fails, fix issues and re-merge OR git revert if already merged

No data loss risk. All changes are code-only and tracked in git.


Getting Started

For the Decision Maker (You)

  1. Read the plan: NODEJS_UPGRADE_PLAN.md (20 min)
  2. Review risk assessment (Medium risk; mitigated by comprehensive testing)
  3. Approve or iterate on the plan
  4. Confirm business requirement for Node 24 (advanced GitHub API scripts)
  5. Assign execution to team member(s) or approve agent execution

For the Team Executing the Upgrade

  1. Review EXECUTION_PROMPTS.md — self-contained prompts per phase
  2. Use QUICK_REFERENCE.md — track progress with checklist
  3. Follow one phase at a time — each phase has clear success criteria
  4. Report blockers — document in project folder (BREAKING_CHANGES_AUDIT.md if issues arise)

Key Decisions Made

✅ Node Version: 24.x (business requirement, future-proof)
✅ Workflow Strategy: All use .nvmrc (single source of truth)
✅ Dependency Update: Run npm update within semver ranges, then npm ci to validate consistency
✅ Branch Strategy: feat/nodejs-upgrade-24 → PR to develop
✅ Testing: Full suite + validation scripts (Phase 3)
✅ Monitoring: 3-day post-merge monitoring (proven protocol)


Decision Template

Once you've reviewed the plan, please confirm:

✓ Plan reviewed and understood
✓ Risk level acceptable (Medium)
✓ Timeline acceptable (~4–5 hours)
✓ Business requirement confirmed (advanced GitHub API scripts)
✓ Assign to: [Agent/Team Member]
✓ Target completion: [Date]

Approval: [Signature / Confirmation]

After Approval

Once you approve, the next steps are:

  1. Verify or create issues for each phase (5 issues total) — use existing GitHub issues if available; create only if needed
  2. Assign to agent(s)
  3. Agent executes phases in order using EXECUTION_PROMPTS.md
  4. Track progress in QUICK_REFERENCE.md
  5. Merge to develop after Phase 5 complete
  6. Monitor workflows for 3 days

FAQ

Q: Why not stay on Node 22?

A: You need Node 24 features for advanced GitHub API scripts and issue maintenance workflows. Also, the .nvmrc is already configured for Node 24, creating a mismatch with package.json.

Q: Will this break anything?

A: Unlikely. Phase 3 runs the full test suite and all validation scripts. We've tested for breaking changes. The risk level is Medium (vs. Low for Node 22), but mitigated by comprehensive testing.

Q: How long does this actually take?

A: ~4–5 hours of execution time, but can be spread over 1–2 days. Most of that is waiting for tests to run.

Q: What if a test fails?

A: Document it in BREAKING_CHANGES_AUDIT.md. We'll either fix the issue or pin the problematic package. Rare (~10% probability).

Q: Can we revert if needed?

A: Yes, easily. All commits are atomic and tracked in git. Revert takes minutes.

Q: Do we need to update DEVELOPMENT.md?

A: Yes. After the upgrade completes, update DEVELOPMENT.md to document Node 24 requirement and link to this project's completion report.


Related Files & Issues

  • Configuration: .nvmrc, package.json, .github/workflows/*, DEVELOPMENT.md
  • Issue: Mismatch between .nvmrc (24) and package.json (>=22)
  • Epic: Infrastructure Modernisation 2026-Q4
  • Related PRs: (None yet; will be created during Phase 5)
  • Previous Upgrade: Node.js 22 Upgrade (July 2026)

Next Steps

For You (Decision Maker)

  1. ✅ Read NODEJS_UPGRADE_PLAN.md (20 min)
  2. ⏳ Review and approve the plan
  3. ⏳ Confirm your approval using the decision template above
  4. ⏳ Create GitHub issues using the issue templates provided

Once Approved

  1. Create 5 GitHub issues (one per phase) using OpenSpec validation
  2. Assign to execution team
  3. Begin Phase 1 (Audit & Documentation)

Project Metadata

  • Created: 2026-08-29
  • Author: Ashley Shaw
  • Stakeholders: DevOps, CI/CD, Infrastructure, Advanced Issue Maintenance
  • Repository: lightspeedwp/.github
  • Status: Planning phase active
  • Approval: Pending user review and confirmation

Related Issues

This project coordinates with:

  • #1733 — Phase 2: Folder Structure & Linking

See Linking Standard for linking patterns.

Visual Workflow

flowchart TD
  accTitle: Node.js 24 Upgrade Workflow
  accDescr: Five-phase execution flow from start through audit, upgrade, validation, workflow standardization, merge, and post-merge monitoring to completion.
  A["Start: Node 24 Alignment"] --> B["Phase 1: Audit"]
  B --> C["Phase 2: Local Upgrade"]
  C --> D["Phase 3: Validation"]
  D --> E["Phase 4: Workflows"]
  E --> F["Phase 5: Merge"]
  F --> G["3-Day Post-Merge Monitoring"]
  G --> H["Project Complete"]

  classDef start fill:#E8F5E9,stroke:#2E7D32,stroke-width:2px,color:#1B5E20;
  classDef phase fill:#fef3c7,stroke:#b45309,stroke-width:2px,color:#4a2c00;
  classDef monitoring fill:#E0F2F1,stroke:#00695C,stroke-width:2px,color:#004D40;
  classDef done fill:#E8F5E9,stroke:#2E7D32,stroke-width:2px,color:#1B5E20;

  class A start;
  class B,C,D,E,F phase;
  class G monitoring;
  class H done;
Loading

This project is ready for comprehensive planning. Review the plan, ask questions, and approve when ready!