The 2025.09.15 SRU Cycle started

cycle: 15-Sep through 12-Oct (4 weeks)

         10-Sep   Last day for kernel commits and Nvidia graphics drivers.
15-Sep - 19-Sep   Kernel prep week.
22-Sep - 10-Oct   Bug verification & Regression testing.
 Week of 13-Oct   Release to -updates.

Kernel Versions

plucky:
    linux:               6.14.0-33.33
noble:
    linux:               6.8.0-86.87
    linux-hwe-6.14:      6.14.0-33.33~24.04.1
jammy:
    linux:               5.15.0-158.168
    linux-hwe-6.8:       6.8.0-86.87~24.04.1 (predicted)

IMPORTANT NOTICE (2025.10.13 SRU Cycle)

Due to internal events taking place during the cycle the duration has been extended to 5 weeks. A following normal SRU cycle would release rather close to the end of the year. To avoid regressions / issues persisting across the change of year, the upcoming 2025.10.13 cycle will be the last normal SRU cycle in 2025.

For CVEs and important fixes/changes we plan to use the s2025.10.13 security cycle as a cleanup release. It will contain no upstream stable sets and changes submitted after Oct-08 will require explicit requesting and approval to be picked into s2025.10.13!

cycle: 13-Oct through 16-Nov (5 weeks)

         08-Oct   Last day for kernel commits and Nvidia graphics drivers.
13-Oct - 17-Oct   Kernel prep week.
20-Oct - 14-Nov   Bug verification & Regression testing.
 Week of 17-Nov   Release to -updates.